Construction Update | July 25, 2024

In observance of Pioneer Day, Wednesday, July 24, all construction activities will pause on Tuesday, July 23 at 3 p.m. Work will resume on Thursday, July 25, at 6 a.m.

 

3500 West (SR-108) at 5600 South (SR-97) Intersection*

Eastbound and westbound traffic will shift at the intersection of 3500 W and 5600 S to accommodate paving work, beginning Thursday, July 25 through early Fall.

See traffic pattern graphic below.

Along 5600 South (SR-97)*

Crews are completing curb and gutter installation activities on the south side of 5600 South between 2700 W and 3100 W in preparation for paving activities this summer. Crews are finishing setting retaining walls and completing bridge abutment activities along the Union Pacific Railroad (UPRR) bridge at 2700 W throughout the month of July. Drivers can expect lane shifts, occasional flagging operations, adjacent cross street closures and short-term delays along the corridor.

 

Crews will be completing nighttime utility mainline crossing activities along 5600 South between 2300 W and 2050 W from 7 p.m.– 7 a.m. beginning as early as, July 29 for approximately 2-weeks. Residents can expect noise, dust, and nighttime lighting.

 

Along Wardleigh Road and Missile Way Intersection*

Crews will complete drainage work along Wardleigh Road between the Freeway Park Dr. and Missile Way intersection this weekend, July 26-27 from 6 a.m. to 5 p.m. Traffic will be shifted to one lane in each direction during this work. Drivers can expect minimal delays.

 

Freeway Park Dr. and 5600 South (SR-97)*

The intersection of Freeway Park Dr. and 5600 S. will close as early as early as Monday, July 29 for approximately 1-week to accommodate waterline work. Business access will be maintained. Drivers will need to detour via Riverdale Rd.

 

Along 5600 South (SR-97) at 2950 W facing west.


Weber School District – Summer Lunch Program

The state Summer Food Service Program (SFSP) offers the opportunity for local schools in Weber School District to provide free nutritious meals to kids during summer break.

 

You can find more information about the summer lunch program here.

 

 

Ongoing Work

I-15 NB Structure at 5600 South (SR-97)

Crews will continue construction activities that include, drainage work, forming the deck, adding overhangs, and completing paving activities. 

 

Along 5600 South (SR-97)

Third-Party utility work is taking place along 5600 South (SR-97) on the north and south sides in park strips at intermittent locations. Some properties along the corridor may be in a Public Utility Easement (PUE). This easement ensures that vital services, such as power lines, water pipes, gas lines, and communication cables can be acessed and maintained efficiently.  Restoration work will be happening as utility work progresses through summer. Please contact the project team if you have any questions. 

 

Moving Utility Operations and Nightwork continues along 5600 South (SR-97)

 

In partnership with Roy City, crews are continuing installation of a new waterline along 5600 South. To minimize impacts to water service, work is taking place during nighttime hours, approximately (7 p.m. – 5 a.m.). This work will be a moving operation and take place in various locations throughout the corridor.

 

Crews will temporarily close intermittent locations throughout the corridor. Impacted neighborhood residents will be notified of culinary water shut-offs and road closures by a flyer left on their front door. Work is expected to continue through summer 2024.*

 

What to Expect:

  • Noise, dust, vibration, and nighttime lighting
  • Short-term culinary water shut-offs (approximately from 9 a.m. – 5 p.m.)
  • Occasional cross street road closures
  • One-way traffic operations with flaggers
  • Construction vehicles and crew members in the area

 

Utility work along 5600 South (SR-97) at 3000 W. facing north.

 

Closure at DR&G Trail near 2700 W

Crews are continuing work at the DR&G trail from 5600 South to 5200 South to accommodate the building of the new pedestrian bridge structure that will go over 5600 South. Crews are using a Continuous Flight Auger (CFA) drilling technique, which provides exceptional speed and efficiency. Unlike traditional methods with multiple stages–drilling, casing installation and concrete placement, CFA combines all these steps into a single, process. Concrete is pumped through the auger simultaneously with the extraction of the auger from the ground.

             Continuous Flight Auger (CFA) operation along 5600 South (SR-97) at 2700 W DR&G

pedestrian trail facing northeast.

 

The trail closure is in place through late fall 2024. Pedestrians are encouraged to detour via 2700 W. 

 

 

Utility and drainage work along the south side of 5600 South will continue intermittently throughout the corridor.

 

Along 5600 South, crews will continue setting retaining panels and other activities around the UPRR (Union Pacific Railroad) bridge and along the north side at 2300 W through the month of June. Drivers can expect lane shifts, one-way flagging operations, adjacent cross street closures, and short-term delays along the corridor.

 

Storm drain crane operation along 5600 South (SR-97) at 2500 W facing east.


I-15 Collector Distributor (CD) Structure at 5600 South (SR-97)

Timelapse video of crews completing and setting CD structure girders (beams) in February

 


Know Before You Go! Download the UDOT Traffic App Today!

 

The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways.

 

The available information includes:

  • Emergency and incident notifications
  • Construction alerts
  • Anticipated delays and lane closures
  • Road conditions
  • Travelwise alerts
  • A zoomable, scrollable map-based display

 

*download available for iPhone and Android devices

Learn more about Travelwise Tips here.

 

 

Contact Us

Join our mailing list! Email us at 5600south@utah.gov to receive updates about the project.

The project team is here to help. Please call or email with any questions or comments.

Hotline: 385-383-6576

Email: 5600south@utah.gov 

 

*Construction schedules are subject to change due to weather, utility, material and equipment delays.

 

Project impacts to travel can be found on the UDOT Traffic Website, www.udot.utah.gov/traffic or by downloading the UDOT Traffic app. 

Schedule 

live
live
Right-of-Way Acquisition (2022-2024)

live
live
Final Design (Spring 2024)

live
live
Construction Began (Summer 2023)

Work Days: Monday - Friday, 7 a.m. - 5 p.m.

What to Expect:

  • Daytime work
    • Occasional night and weekend work
      • (7 p.m.-7 a.m.)
  • Heavy equipment, support vehicles, and crew members
  • Temporary access restrictions
  • Ocassional lane shifts and closures 
  • Alternate routes 
  • Increased noise, dust and vibration

planned
planned
Project Completion (Fall 2026)

Area Projects 

Learn more about the Western Weber Active Transporation Plan project.  

Learn more about the 1800 North project.  

Learn more about the 2000 West project.