Overview

Project Description

The Utah Department of Transportation is replacing three bridges in Riverdale. The 4400 South bridge over I-15 was successfully rebuilt, and it reopened on June 16, 2026. Work continues on the two ramp bridges carrying traffic to and from I-15 to I-84 over 4400 South. This work began August 11, 2025 and is expected to conclude in fall 2026. 

A map of the project work zone. Red on 4400 South above I-15, green on 4400 South east of that.

4400 South (under I-84) between 1250 West/Parker Drive and Cozy Dale Drive is open while crews construct the bridge walls. Traffic is currently limited to one lane. Flaggers will direct traffic. Travelers can expect delays of 15 minutes or more until both lanes open in the morning.

Sign up to receive weekly email updates using the form at the bottom of this page. 

To improve quality of life and accommodate the ever-growing needs of our state, UDOT is committed to keeping Utah moving both now and in the future. We monitor the health of our infrastructure because safety is our priority. Inspections allow us to act well in advance to replace structures on their way towards disrepair. We are partnering with the cities of Roy and Riverdale to make these improvements to local infrastructure to reduce disruption to the community. 

*Sign up to receive email updates.

Contact the Public Involvement Team

Hotline: 855-925-2801 (Project Code 3107)

Email: i84bridges@utah.gov

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.

Project Schedule

Project Timeline

live
live

Construction

August 2025 - Fall 2026

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

complete
complete

Advertisement

Completed Spring 2025.

complete
complete

Design

Completed January 2025. 

complete
complete

Engineering

Completed October 2024.

complete
complete

Environmental Document Approval

Completed March 2024.

complete
complete

Project Kick-off

Completed October 2023.