Project Description

We will replace three bridges in Riverdale, including 4400 South over I-15 and two ramp bridges carrying traffic to and from I-15 to I-84 over 4400 South. This work began August 11, 2025. 

Meet the Contractor Open House

You are invited to attend our Meet the Contractor public open house on January 14, 2026, from 5:30-7:30 p.m. at the Riverdale Community Center. Come ask questions and learn more about the detour routes, schedule, short-term impacts and long-term benefits of this project.

 

Holiday Break

Our crews will pause all construction from Tuesday, December 23, through Monday, January 5, in observance of Christmas and the New Year.

4400 South Bridge over I-15 Closure

4400 South between 1600 West/Airport Road and Cozy Dale Drive is closed while crews rebuild the bridge over I-15.

With the end of the government shutdown, UDOT has been able to resume communication with the FAA to obtain approval to work near the Ogden Airport flight path. Construction on the 4400 South bridge over I-15 will resume Monday, December 1, when our crews begin driving steel beams into the ground on the west side for the new bridge support walls. The bridge is anticipated to reopen in April 2026.

The public outreach team intends to host a rescheduled Meet the Contractor open house once a schedule is more firmly set. The team continues to work with Riverdale City, its police department, and individual businesses to address concerns related to the detour around 4400 South.

4400 South (under I-84) between 1250 West/Parker Drive and Cozy Dale Drive is open while crews construct the bridge walls. One lane in each direction will be open during the day. However, traffic will be limited to one lane overnight from 7 p.m. to 7 a.m. Flaggers will direct traffic. Travelers can expect delays of 15 minutes or more until both lanes open in the morning.

DURING CONSTRUCTION:

  • Emergency vehicles WILL have access on 4400 South Parker Drive and Cozy Dale Drive during the closure
  • Pedestrian access remains OPEN on the pedestrian overpass
  • 4400 South (to the east), 900 West, Riverdale Road and Cozy Dale Drive should be used as detour routes
  • UTA’s Route 640 will be suspended along 4400 South and 1900 South. Riders can reach Route 640 at Riverdale Road between 1150 West and 1900 West
  • Patrons of the Ogden Airport should use 31st Street to access the airport in the timeliest manner.

Sign up to receive weekly email updates using the form at the bottom of this page. 

To improve quality of life and accommodate the ever-growing needs of our state, UDOT is committed to keeping Utah moving both now and in the future. We monitor the health of our infrastructure because safety is our priority. Inspections allow us to act well in advance to replace structures on their way towards disrepair. We are partnering with the cities of Roy and Riverdale to make these improvements to local infrastructure to reduce disruption to the community. 

Question title

*Sign up to receive email updates.

Contact the Public Involvement Team

Hotline: 855-925-2801 (Project Code 3107)

Email: i84bridges@utah.gov

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.

Project Schedule

live
live
Construction

August 2025 – August 2026

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

complete
complete
Advertisement

Spring 2025

complete
complete
Design

Ongoing. Expected completion: January 2025. 

complete
complete
Engineering

Ongoing. Expected completion: October 2024

complete
complete
Environmental Document Approval

March 2024

complete
complete
Project Kick-off

October 2023