I-15 | St. George Boulevard to Bluff Street | Improved
I-15 | St. George Boulevard to Bluff Street | Improved
UDOT will widen I-15 through St. George from two to three lanes in both directions, and raise the interstate as necessary to build new local connections under I-15 at 400 E and 900 S.
Environmental Reevaluation Document
The environmental reevaluation for this project was finalized on July 31, 2025. The document can be viewed and downloaded on the Public Hearing Tab, along with materials presented at the Public Hearing on June 25, 2025.
Planned Improvements
We are designing improvements for Interstate 15 (I-15) through St. George, Utah, to accommodate the area’s long-term transportation and mobility needs. Improvements will include the following:
Widen northbound and southbound I-15 from two lanes to three lanes between Bluff Street (Exit 6) and St. George Boulevard (Exit 8)
Replace structures over 100 South and raise I-15 as needed
Replace structures over 700 South and raise I-15 as needed
Raise I-15 and construct new structures over 400 East and 900 South to establish new local connections
under I-15Coordinate the realignment of several utilities and installation of new utilities
Improve various drainage facilities along and under I-15
Design improvements at 700 South to facilitate a future interchange
A reevaluation of an October 2023 Environmental Assessment (EA) iwas completed to incorporate the addition of the new overpasses and local connections at 400 East and 900 South, which were not part of the original environmental document. A public hearing was held June 25, 2025.
The reevaluation includes additional noise analysis related to the new overpasses. After the public hearing, identified impacted property owners and tenants will be asked to vote to help determine the final noise wall locations.
This UDOT noise wall video explains our noise wall balloting process.
The design phase is anticipated to take about 18 months, from fall 2024 through early 2026. Construction is expected to last about two years from mid-2026 through 2028.
Project information was shared at the 2025 Dixie Regional Transportation Expo. The information boards are linked here.