Construction Update | Oct. 2, 2025 

 

I-15 and 5600 South (SR-97)

Crews are completing cast-in-place barrier work in the I-15 median at the 5600 South structure. With removals finished, roadway section reconstruction is now underway. Barrier work continues on the northbound side, and once complete, crews will shift to the southbound side. Drainage work along I-15 northbound mainline is scheduled to begin in mid-October. In additon, painting of structures and MSE wall coating will continue through next week. Drivers can anticipate minimal to intermediate delays during peak hours around the interchange.

 

Freeway Park Dr. and Riverdale Rd.

Work is progressing on the north end with concrete paving for sidewalks and flat roadway areas along with barrier activities. Next week, crews will begin median work. Drivers can expect one-way flagging with minimal to intermediate delays during the daytime. The Riverdale Rd. exit (Exit 338B) will remain open to traffic.

16391_5600 South - Freeway Park Drive and I-15 NB

I-15, Riverdale Rd. CD and Freeway Park Dr. facing northwest.

 

5600 South, 1900 West and UPRR Bridge Area

At the 1900 West intersection, crews will begin removals on the northeast corner early next week, with paving planned for Oct. 10. Drainage improvements, including new manholes and catch basins, are also underway and will continue through the month of October.

 

Over the Union Pacific Railroad bridge (UPRR) along 5600 South between 2700 South and 2050 West, crews poured sidewalks on the south side earlier this week and will now move forward with striping and fence installation along the edge of the bridge deck. Additional curb, gutter, and barrier work will take place along 2700 South and extending toward the UPRR bridge. Drivers can expect minimal to intermediate delays as traffic shifts take place during this work.

16391_5600 South - UPRR bridge work

Along 5600 South over UPRR bridge facing east.

 

1900 West & 5600 South – Back to Standard Intersection

Last weekend, crews removed the temporary Thru-U traffic pattern at 1900 West and 5600 South (SR-97). The intersection is now in a standard configuration.

 

Driver Caution: Stay alert and watch for new overhead and lane designation signage. Drive carefully through the intersection as nearby improvements are still under construction.

16391_5600 South - 1900 West Intersection

                                                         1900 W and 5600 South (SR-97) intersection facing east.

 

Pedestrian Safe Walking Routes

Safe walking routes were updated to include the activated HAWK (High-Intensity Activated crossWalk) light at 2100 West along 5600 South. Drivers: Slow down and be aware of the designated safe walking routes along 5600 South. Stay alert, watch for students and pedestrians in the area.

 

Pedestrian Safety

Prioritize pedestrian safety while navigating through our work zones. Here are some tips to keep in mind:

  • Stay Alert – always be aware of your surroundings. Look out for construction signs, workers, and potential hazards
  • Use Designated Pathways – these paths are designated to keep you safe from construction activities
  • Avoid Distractions – Refrain from using your phone or wearing headphones while walking through construction areas
  • Wear Visible Clothing – Wear bright or reflective clothing, this can help ensure your seen by workers and drivers

 

Let's work together to keep everyone safe!

16391_5600 South - Safe Routes Updated_English

 

16391_5600 South - Safe Routes Updated_Spanish


4800 South Closure & Detour – Sept. 30 - Oct. 1

Beginning as early as Tuesday, Sept. 30 and Wednesday, Oct. 1 from 7 a.m. to 5 p.m. each day, crews will be removing the Union Pacific Railroad ties to accommodate construction activities. During this time, the corner of 4800 South and 1750 West will be closed. Local and through traffic will be detoured to Riverdale Rd.

 

Drivers– please allow extra travel time to reach your destination and use caution in the work zone. For more information, use suggested detour route below.


Riverdale Exit Closure & Detour – Sept. 21-28

From Sunday, Sept. 21 through Sunday, Sept. 28, the Riverdale Rd. exit (Exit 338B) will be closed to accommodate milling, paving, and barrier work near Riverdale Rd.

 

Detour Route:

  • Exit at 5600 South
  • Travel eastbound on 5600 South, use Freeway Park Dr. to reach Riverdale destinations

 

Important: Drivers, please be aware of this temporary traffic pattern change and plan extra travel time.

 

 

 

 

I-15 Riverdale Exit and Freeway Park Dr. Access facing southwest.


Ongoing Work

5600 Corridor

Work is progressing along the 5600 South corridor as crews complete curb, gutter, and driveway tie-ins. Coordination with property owners will continue throughout this phase of construction. Occasional road closures may be necessary to while crews pour and finish concrete surfaces such as sidewalks, driveways and curbing.

 

Current Street Closures:

  • 2100 West (North side) – Right turn in, right turn out only from 5600 South through early October*
  • 2700 West (South side) – Closed Sept 8. – for approximately 4-weeks*
  • 3375 West (North side) – Closed Sept. 8 – for approximately 3-weeks*
  • 2050 West – is now open!

 

Drivers use alternate routes and expect minor delays.

Overview of the UPRR bridge.

 

 


5600 South (SR-97) – Bridge Beam Installation

Late summer, crews successfully installed bridge girders (beams) on the south side of 5600 South bridge over the Union Pacific Railroad (UPRR). This operation was completed over night, each night throughout the weekend, and required long hours, a large support crew, and utilitizing state-of-the-art equipment to ensure a safe and efficient installation.

More details of the bridge installation will be shared in future updates.

Crews completed preparation activities to install the new bridge girders over the UPRR bridge.


I-15 NB Off-Ramp and Riverdale Rd. Access – Exit 338

Earlier this summer, the I-15 northbound off-ramp at Exit 338 (exit 338B) shifted onto the new overpass, which will provide direct access to Riverdale Rd.

 

What to Expect:

  • A new traffic pattern over the completed overpass
  • Updated overhead signage
  • New lane markings
  • Adjusted traffic flow into Riverdale
  • Drivers, be alert for changes in overhead signage, lane markings and traffic flow.

 

Improved Flow and Faster Access

This new traffic pattern is designed to improve traffic flow through the area. By shifting the off-ramp onto the new overpass, drivers will no longer need to stop at the previous ramp intersection, reducing congestion and travel delays. The direct connection to Riverdale Rd. allows for smoother, more efficient movement of vehicles–resulting in a safer and more streamlined driving experience.


Know Before You Go! Download the UDOT Traffic App Today!
The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways. 

The available information includes:

  • Emergency and incident notifications
  • Construction alerts
  • Anticipated delays and lane closures
  • Road conditions
  • Travelwise alerts
  • A zoomable, scrollable map-based display


*download available for iPhone and Android devices

Learn more about Travelwise Tips here.

Contact Us

Join our mailing list! Email us at 5600south@utah.gov to receive updates about the project.

The project team is here to help. Please call or email with any questions or comments.

Hotline: 385-383-6576

Email: 5600south@utah.gov 

 

*Construction schedules are subject to change due to weather, utility, material and equipment delays.

 

Project impacts to travel can be found on the UDOT Traffic Website, www.udot.utah.gov/traffic or by downloading the UDOT Traffic app. 

 

Driver Safety: Please prioritize safety while driving through the construction zones.

  • Slow down and maintain a safe following distance
  • Obey speed limits and follow posted signage
  • Be alert for crew members and equipment
  • Avoid distractions and be prepared for detours and lane changes
  • Drive patiently and cautiously to ensure everyone's safety on the road

Schedule 

complete
complete
Right-of-Way Acquisition (2022-2025)

complete
complete
Final Design (Winter 2025)

live
live
Construction Began (Summer 2023)

Work Days: Monday - Friday, 7 a.m. - 5 p.m.

What to Expect:

  • Daytime work
    • Occasional night and weekend work
      • (7 p.m.-7 a.m.)
  • Heavy equipment, support vehicles, and crew members
  • Temporary access restrictions
  • Ocassional lane shifts and closures 
  • Alternate routes 
  • Increased noise, dust and vibration

planned
planned
Project Completion (Fall 2026)

Area Projects 

Learn more about the 1800 North project.  

Learn more about the 2000 West project.  

Learn more about the 4400 South project.