Project Updates

June 4 - June 18

Schedules are subject to change due to weather and material/equipment availability.

 

Know before you go! Check UDOT Traffic before hitting the road. 

 

Upcoming Impacts

1800 North

Upcoming side street closures are planned on the north side of 1800 North:

  • 810 West is currently closed through June 13.
  • 725 West will be closed June 16 - 20.
  • 630 West will be closed June 23 - 27.
Upcoming road closures maps with dates.
 

Work near the railroad tracks continues through June 25 taking place 24-hours a day to allow crews to place utilities under the railroad tracks. This 24/7 operation was made possible through coordination with UTA and Union Pacific Railroad to minimize impacts to rail traffic. 

Additional side street closures as possible along 1800 North between Main Street and 2000 West. When closed, follow the posted detour signs to access the neighborhood streets.

 

Main Street

As early as Thursday, June 12, the asphalt on the west side of Main Street between 1800 North and 1600 North will be removed in preparation for waterline work and the road widening on 1800 North.

 

Traffic has been shifted to the east side of Main Street between 1600 North and 1800 North for this work. Property owners on the west side of Main Street between 1600 North and 1800 North may have short-term driveway access interruptions while work crosses driveways.

 

Ongoing Impacts

I-15

I-15 northbound has been reduced to 11' wide lanes while crews work on the new I-15 interchange. Wide loads should use caution while driving through the area.

Crews are currently working in the area east of I-15 where the new interchange will be built. Crews have placed the steel supports for the new interchange bridge and are installing drainage and sewer lines under the future I-15.

 

Main Street

Utility and other work continues to take place on the shoulder areas of Main Street. Drivers and pedestrians should use caution in work areas and be prepared for shifting traffic patterns. Watch for closures and follow detour signs.

 

1800 North

Work continues on new traffic signal foundations at 250 West and 1000 West.

Trenching continues on the north side of 1800 North for a joint underground utility trench. While work is taking place, driveways may have temporary short-term access interruptions.

Utility work continues along the entire corridor. See our utility information on the Project Overview tab to learn more about the coordination and number of utility companies working on this project. 

Area residents may experience an increase in constructin related noise, dust, and vibration.

 

Road Closures

475 West

Through July, 475 West will be closed at 1800 North while crews work in bore pits to run utility lines under the railroad tracks. While 475 West is closed, please use 400 West and 1600 North as a detour route. 

475 West is closed at 1800 North while crews install a new water line. This is the detour map showing 475 West closed and traffic detouring to 400 West.

Sunset City Central Park

Access to the Sunset City Central Park will have short-term access closures on 1800 North while crews install a new water line on the south side of 1800 North. When the driveway is closed, use 250 West to 1675 North to access the park.

Detour map for Sunset City Central Park. The 1800 North accesses will be closed while work takes place and drivers should use 250 West to 1675 North to access the park.

 

 

Traffic/Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

 

UTA LogoUTA Bus Routes 640 & 470 - Due to construction activities, the bus stops within the work areas may have temporary closures and/or stop adjustments. Visit UTA's website for specific stop information.
 

 

Schedule

complete
complete
Project Design: Fall 2021 to Spring 2025

Kick-off December 2021

complete
complete
Right of Way Acquisition: Summer 2023 to Spring 2025

complete
complete
Environmental Reevaluation: Winter 2022 to Summer 2023

complete
complete
Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
In-Person Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
Substantial Design Complete: January 2024

live
live
Start Construction: March 17, 2025

Work Hours: 7:00 a.m. - 6:00 p.m. 

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability. 

planned
planned
End Construction: Fall 2027

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-383-6576

Email: 1800north@utah.gov

 

Stay Informed

To receive weekly construction updates, fill out the form on the Contact Us! page or contact the public information team at the email address above and enter "Project Updates" in the subject line.  

Area Projects

Learn more about the 5600 South project (Roy).

Learn more about the 2000 West project (West Point to Clinton).

Learn more about the SR-108 project (Clinton to West Haven).