Project Updates

June 26 - July 3

Schedules are subject to change due to weather and material/equipment availability.

 

Know before you go! Check UDOT Traffic before hitting the road. 

 

Upcoming Impacts

 

I-15

On July 2, at 4:00 a.m., Rocky Mountain Power will remove a power line crossing over I-15 near 1300 North. To facilitate this, the Utah Highway Patrol will conduct a traffic slowdown on both northbound and southbound I-15 while crews disconnect the wires and clear them from the road. 

Drivers can expect delays of up to 30 minutes while this work takes place. 

 

1800 North

Side street closures are planned on the north side of 1800 North hile crews complete utility work:

  • 810 West will open by the end of the day this Friday.
  • 630 West will open by the end of the day this Friday.
  • 725 West will be closed June 30 - July 11.
  • 550 West will be closed June 30 - Jul 11. 
  • 550 West (south side) is currently closed through July 3.
  • 475 West (south side) is currently closed through July 31.

This map shows the current and upcoming side street closures.

 

Additional side street closures are possible along 1800 North between Main Street and 2000 West. When closed, follow the posted detour signs to access the neighborhood streets.


Ongoing Impacts

I-15

I-15 northbound has been reduced to 11' lane width. Wide loads should use caution driving through the area.

 

In the area east of I-15, crews are building up the road and installing new retaining walls for the new interchange, as well as installing new water, sewer, and storm drain lines under the future I-15.

 

Main Street

Traffic has been shifted to the east side of Main Street between 2000 North and 1600 North while crews remove the old road and install new water lines.

Utility and other work continues on the shoulders of Main Street. Drivers and pedestrians should use caution in work areas and be prepared for shifting traffic patterns. Watch for closures and follow detour signs.

 

1800 North

Utility work continues along the entire corridor with the dozens of utility companies with infrastructure along 1800 North.

From the driver’s eye view, this can look like repetitive work – digging up a trench, laying pipe, compacting it, and doing it all over again for the next service. The network of pipes and conduit under the road can be as congested as the cars that drive on top of it. Additionally, utilities have spacing requirements to keep clearance from other pipes in their final placement.

It is critical to complete this work before pavement replacement to prevent future impacts to the roadway.


Area residents may experience an increase in construction related noise, dust, and vibration.

 

Closures

Sunset City Central Park

Access to the Sunset City Central Park will have short-term access closures on 1800 North while crews install a new water line on the south side of 1800 North. When the driveway is closed, use 250 West to 1675 North to access the park.

Detour map for Sunset City Central Park. The 1800 North accesses will be closed while work takes place and drivers should use 250 West to 1675 North to access the park.

 

 

Traffic/Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

 

UTA LogoUTA Bus Routes 640 & 470 - Due to construction activities, the bus stops within the work areas may have temporary closures and/or stop adjustments. Visit UTA's website for specific stop information.
 

 

Schedule

complete
complete
Project Design: Fall 2021 to Spring 2025

Kick-off December 2021

complete
complete
Right of Way Acquisition: Summer 2023 to Spring 2025

complete
complete
Environmental Reevaluation: Winter 2022 to Summer 2023

complete
complete
Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
In-Person Public Hearing - Re-Evaluation of the Environmental Impact Study

complete
complete
Substantial Design Complete: January 2024

live
live
Start Construction: March 17, 2025

Work Hours: 7:00 a.m. - 6:00 p.m. 

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability. 

planned
planned
End Construction: Fall 2027

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-383-6576

Email: 1800north@utah.gov

 

Stay Informed

To receive weekly construction updates, fill out the form on the Contact Us! page or contact the public information team at the email address above and enter "Project Updates" in the subject line.  

Area Projects

Learn more about the 5600 South project (Roy).

Learn more about the 2000 West project (West Point to Clinton).

Learn more about the SR-108 project (Clinton to West Haven).