Overview

Project Overview

This project will complete the improvements between Antelope Drive in Davis County and Hinckley Drive in Weber County. SR-108 will be reconstructed and widened to accommodate future travel demand and to improve safety conditions. The design will include five lanes, widened shoulders, improved sidewalks and a multi-use path. 

 

Benefits:

  • Meet the current and future traffic demands
  • Accommodate and support all modes of transportation
  • Provide a safe and efficient traveling experience for commuters of every kind
  • In partnership with Clinton, Roy and West Haven, make improvements to local infrastructure

Image showing cross-section of the proposed new road

New Cross Section of the Road

View the project design by clicking the map below. 

Project map. Click to view the full road design.

Schedule

Project Timeline

live
live

Project Design

Summer 2024 to Winter 2026

planned
planned

Right-of-Way Acquisition

Spring 2025 to Winter 2026

planned
planned

Construction

Spring 2027 to Fall 2029

complete
complete

Environmental Re-Evaluation

Summer 2024 to Summer 2025

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-925-2801 project code 7292

Email: SR108@utah.gov

Stay Informed

To receive update emails, please contact the public information team at the email address above and enter "Updates" in the subject line.