NOTICE [UPDATED 7/18]:

#1: Motorists should expect high traffic volumes and delays, particularly westbound on Friday and Saturday nights - consider alternate routes such as US-40 to SR-189 (Provo Canyon), SR-224 (Empire Pass), or Emigration Canyon via Exit 134 to avoid congestion.
#2: 7/18 & 7/25 Westbound lane closures will begin at 10:30pm. Additionally, crews are working Sunday Night 7/20 into Monday morning 7/21. See 'Impacts & Updates' tab for work hours.
#3: Work Suspension - All lanes remain open 7/23 - 7/24 for the 24th of July holiday

 

Project Description:

The Utah Department of Transportation (UDOT) will resurface I-80 in Parley’s Canyon, from Lower Parleys to exit 134. The project objectives are aimed at preserving the life of the road. This paving process will not only help increase the longevity of the road but also address roadway structural integrity and enhance motorist safety by providing a smoother, more durable road surface.  The on/off ramps along the route will also be resurfaced. Additional work includes variable drainage enhancements, barrier upgrades, refreshed road surface striping, and updated roadside signage.

New pavement on I-80 on-ramp from SR-65

New Pavement |Westbound I-80 On-Ramp from SR-65 (Exit 134) | 06/18/25

I-80 Parleys Canyon Map

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8362

Email: i80parleyspaving@utah.gov

live
live
Start: May 15, 2025

Work Hours: Mostly nighttime; Some daytime work

Days: Monday PM - Sunday AM; Sunday night as necessary

 Check [Impacts and Updates] tab for variable nighttime operations and lane restrictions.

 

May 15 - June 1:  EB travel lane(s) drainage enhancements

June 11:  Paving work begins. See "impacts & updates" tab for details

 

Schedules are subject to change due to weather conditions and material availability. 

planned
planned
Construction End: Late July 2025