7/31 NOTICE:  All parking restrictions lifting along Center St.

Project Description

The Utah Department of Transportation (UDOT) will resurface State Route 150 in Summit County from State Route 32 (Main Street) in Kamas City to six miles east of Samak . The project objectives are aimed at preserving the life of the roadway. This paving process will help increase the longevity of the road surface, address roadway imperfections and enhance motorist safety by providing good skid resistance for vehicles.

Route:  SR-150 |  Start Milepost: 0 -  End Milepost: 6.084

 

Work Schedule Details:

7/10 - 7/12 )  Filling and patching various soft spots along the route.

7/17 - 7/20 )  Tapering and compacting asphalt material along the shoulders.  Adding delineators to the edge of the travel lanes.

7/25 - 7/31 )  Primary resurfacing work.  This is a chip-seal and fog coat overlay process.  Work will begin at the top of the route near the Samak Community, and conclude with some shouldering of the roadway and the addition of permanent travel-lane paint lines.  

7/31 - 8/4 )  Additional miscellaneous work includes roadside signage updates, etc.  Substantially complete!

Schedules are subject to change due to weather conditions and material availability.

 

Schedule

Work Hours: 7am - 7pm

Workdays: Monday - Thursday

Schedules are subject to change due to weather conditions and material availability.

complete
complete
Start Construction: July 10

Crews will begin work along Center Street within town providing some patch work.  This will require some early flagger operations.  By July 20, this early miscellaneous work is anticipated to be completed.  The primary resurfacing work will begin at the top of route near the Samak Community and go to Center Street (SR-39) at Main Street. 

[ See Impacts and Updates tab for traffic control details ]

complete
complete
End Construction: August 2023

Approximately 45 days from construction start

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-990-1050

Email: sr150kamas@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "SR-150 Paving Updates" in the subject line.