ALL LANES HAVE REOPENED ON 9000 SOUTH!

All lanes have reopened on 9000 South. Some lane closures are possible while finish work is completed.

All lanes have reopened on 9000 South. Some lane closures are possible while finish work is completed. 

 

PROJECT UPDATES

Construction Activities July 10 - July 31

Know before you go! Check UDOT Traffic before hitting the road. 

Upcoming and Ongoing Activities

State Street to 700 West

ADA pedestrian ramp work continues on the south side of 9000 South near 600 West. Patrons to the adjacent businesses should use the access from 700 West. This closure will several weeks.

 

Remaing Activities 

The following list of remaining items will be completed through July 31:

  • Median curb on 700 West, between the Jordan River and 700 West, and near 900 West
  • Landscaping
  • Stamped concrete
  • Final lane striping (overnight work)
  • Raise remaining utility lids (overnight work)
  • Final inspection and to do list


Some lane closures are possible while this finish work takes place.

 

*Schedule is subject to change due to weather, equipment, or material delays.

 

Upcoming Road Closure

Work on the railroad bridge near 400 West will require 9000 South to be closed overnight between 11:00 p.m. and 5:00 a.m. This work is not related to the 9000 South project.

As early as Friday, July 11, 2025, eastbound 9000 South will be closed with all traffic being detoured at Sandy Parkway.

As early as Saturday, July 12, 2025, westbound 9000 South will be closed with all traffic being detoured at Monroe Street and I-15.

 

Traffic Information

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Miscellaneous Information

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

complete
complete
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

live
live
End Construction: July 31, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the 9000 South Paving Project (Redwood Road to Bangerter Highway) by UDOT, click here.

To learn more about the State Street Paving Project (9400 South to I-215) by UDOT, click here.