SR-12 Bridge Work
SR-12 Bridge Work
WINTER 2025 UPDATE -
The new Henrieville Bridge on SR-12 is open with traffic flowing in each direction.
Smith Ranch Bridge is now open north of Henrieville on SR-12 to two-lane traffic.
All construction has been suspended for Winter 2025. Crews will return in Spring 2025 to complete final tasks.
SR-12 IS OPEN AND TRAFFIC IS MOVING IN A NORMAL PATTERN.
State Route 12; Henrieville Area Bridge Work
Project Overview
Starting the week on November 20, 2023 The Utah Department of Transportation began removing and replacing the Henrieville Bridge and the Smith Ranch Bridge on State Route 12 in the Henrieville, Utah area.
Henrieville Bridge: The new bridge is open with traffic flowing in both directions.
Smith Ranch Bridge: This bridge is open and traffic is flowing in a normal pattern.
Fall 2024 - Substantial Completion of two new bridges!
The schedule is subject to weather, unforeseen circumstances, supply chain interruptions and other impacts.
Contact the Public Information Team by email henrievillebridges@utah.gov or call the Hotline: 435-531-1358.
The photo shows the newly constructed Smith Ranch Bridge.
Asphalt paving is complete on the southbound lane over the Smith Ranch Bridge. Crews have switched traffic onto the new structure and demolished the old, northbound bridge. Work is now focused on rebuilding the new northbound bridge and roadway.
Below: Concrete pour on northbound Smith Ranch Bridge - October 2024.
Finished Henrieville Bridge below.
Schedule
Contact Information
To contact the public information team with questions or concerns:
Hotline: 435-531-1358
Email: henrievillebridges@utah.gov
Stay Informed
Visit the UDOT Project Page at udotinput.utah.gov/henrievillebridges