The Utah Department of Transportation (UDOT) will resurface State Route 68 in Davis County from 500 S to 400 W.  The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface and enhance motorist safety by resmoothing asphalt.  Additional work includes upgraded pedestrian ramps to meet ADA compliance, varied business access ramp improvements and curb/gutter replacements, refreshed lane and road painting/striping, as well as updated roadside signage.

 

SR-68 Bountiful Paving Map

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

live
live
Start: As early as June 10

Work Hours:

7PM - 7AM; Occasional Daytime Work as necessary

Workdays:

Sunday PM - Thursday AM

 

June 10 - July 10: Pedestrian ramps and curb and gutter upgrades

July 20: Paving begins

 

Schedules are subject to change due to weather conditions and material availability.

 

planned
planned
Construction End: Late August 2025