PROJECT UPDATES

 

Construction Activities July 25 - August 3

Ongoing Activities 

State Street to 700 West

Friday, July 27 starting at 8:00 p.m. and working overnight, crews will complete asphalt repair on 9000 South on the east side of I-15 where the concrete meets the asphalt. This work will reduce the large hump in the road making it safer for motorists and a smoother ride.

  • Motorists can expect lane closures, shifting traffic, and flagging operations on eastbound 9000 South along with the off-ramp from southbound I-15 to eastbound 9000 South while this work takes place. Plan on significant delays and watch for sudden stopping traffic.

9000 South I-15 road work map

Night work for the mill and overlay (re-asphalting) of this section is scheduled to begin as early as August 18. This work will last through the end of August. 

 

700 West to 900 West

Starting at 9:00 a.m. Saturday, July 28 and lasting through 5:00 p.m., crews will close one westbound lane on 9000 South while excavation takes place for a Jordan Valley Water vault. 

  • Motorists can expect lane closures and significant traffic delays. Motorists should consider an alternate route. 

Traffic has been shifted to the outside lanes over the Jordan River. Crews are currently removing the old bridge and preparing work for the new bridge.  

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 South. See the detour map below.

 River Oaks Driving Range Detour Route

 

900 West to 1300 West

Overnights starting Sunday, July 29 starting at 8:00 p.m. lasting through August 3, crews will have lane closures on 9000 South at 1300 West to install a storm drain line across 9000 South. 

  • Motorists can expect lane closures, shifting traffic, and flagging operations. Motorists should be prepared for sudden stops. 

Roadway excavation on the south side of 9000 South continues along with storm drain installation. This work may require short-term driveway access interruptions. Alternate business accesses are open and posted.

 

1300 West to Redwood Road

The south leg of 1510 West at 9000 South will be closed through July. Residents and business should follow the detour map below.

1510 West closure detour map

Roadway excavation on the south side of 9000 South continues along with storm drain installation. This work may require short-term driveway access interruptions. Alternate business accesses are open and posted.

*Schedule is subject to change due to weather, equipment, or material delays.

 

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographics as of May 1, 2024.

Built/Installed

9000 South Infographic of installations May 1, 2024

Removals

9000 South Infographic of removals May 1, 2024

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2024. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map.

This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 1, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the Redwood Road Renewed (9000 South - 6600 South) project by UDOT, click here.

To learn more about the Dominion Energy Gas Feeder Line 34 (1300 West from 7800 South to 11400 South), click here.