PROJECT UPDATES

 

Construction Activities March 20 - March 30

Know before you go! Check UDOT Traffic before hitting the road. 

Ongoing Activities 

1300 West Sewer Line Work

Private utility lines are being installed for a new development south of 9000 South on 1300 West. This work is expected to take several weeks. Plan on delays and turning movement restrictions while work is taking place.

 

700 West to 900 West

Work continues on 700 West including upgraded storm drains, new asphalt, additional sidewalks, curb, and gutters. During this work, 700 West will be restricted to NORTHBOUND only. All southbound traffic will be detoured at Sandy Parkway. Local two-way traffic will be allowed between 8400 South and 8800 South. Click here for the detour map.

 

900 West to Redwood Road 

As early as March 29 and 30, traffic on 9000 South between Redwood Road and 700 West will be shifted to the south side the road. This will provide crews space to reconstruct pedestrian ramps, repair concrete, and replace asphalt on the north side of 9000 South. 

As early as March 31, the sidewalk on the north side of 9000 South will be closed while crews rebuild sections of the sidewalk. Please use the sidewalk on the south side of 9000 South as a detour route. Pedestrians should follow posted detour signs at closed sections.

As early as April 14, crews will begin removing asphalt on the north side of 9000 South starting at 700 West and working west toward Redwood Road. Business driveways, residential driveways, and side streets will remain open during the work except during a few specific activities:

  • Asphalt removal
  • Preparatory work to replace asphalt
  • Asphalt placement
When driveways and/or side streets are closed, use Redwood Road, 1510 West, or 1300 West to access businesses or residential areas. 

 

Work continues to install curb, gutter, and sidewalk on the north side of 9000 South between the Utah Islamic Center and the Rocky Mountain Power substation. Patrons to the Utah Islamic Center and adjacent office building may only enter from the business driveway to the west of the center.

 

Work continues on the southeast corner the the 9000 South Redwood Road intersection with a northbound lane closure and driveway access interruptions to the adjoining businesses. Drivers should plan on extra time through this area. This work will last through March 31 and patrons to the business complex should use accesses on Redwood Road or further east on 9000 South. See the map for additional information. See the map for alternate accesses.

 

Landscaping is being installed in the park strips on the south side of 9000 South between 1000 West and Redwood Road. Park strips will include drip irrigation and water-wise plantings. 

 

Nearby residents and business may have an increase in noise, dust, and vibration as work takes place.

*Schedule is subject to change due to weather, equipment, or material delays.

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2025. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map. This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

700 West is open for northbound traffic between 8800 South and 9000 South with local two-way traffic allowed between 8400 South and 8800 South. Click here for the detour map.

 

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 SouthDrivers should not drive into the work zone as hazards may be presentClick here for the detour map.

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Miscellaneous Information

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographics as of December 31, 2024.

 

Did you know?

Our crews have used over 647,000 pounds of reinforced steel during this project - most on the new bridge over the Jordan River! That's more than a 747 weighs! 

Project comparison on the amount of steel used in the 9000 South project versus the weight of a 747 plane.

Infographic as of December 31, 2024 showing the project 76% complete and amount of materials used/installed.

Infographic as of December 31, 2024 showing the project 76% complete and amount of materials removed.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 31, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the 9000 South Paving Project (Redwood Road to Bangerter Highway) by UDOT, click here.