PROJECT UPDATES

 

Construction Activities October 23 - November 4

Ongoing Activities 

State Street to 700 West

Crews have completed the work in this area.

 

700 West to 900 West

Traffic has been shifted to the outside lanes over the Jordan River as crews place rebar and form the center section of the bridge over the Jordan River. Crews also work on the asphalt approaches on either side of the center section of the bridge. 

 

900 West to Redwood Road 

Weather permitting on Tuesday, October 29 at 10:00 a.m., crews will hang a new signal mast arm for eastbound 9000 South at Redwood Road requiring the closure of the road for up to 10 minutes. Police officers will be directing traffic. 

As early as Friday, November 1 at 8:00 p.m. through Monday, November 4 at 5:00 a.m., crews will close 1300 West across 9000 South while crews rebuild the intersection. Traffic on 1300 West will be allowed to turn right onto 9000 South along with 9000 South traffic being able to turn right onto 9000 South. No left turns will be allowed. Use Redwood Road as a detour route.

1300 West 9000 South Intersection work detour map for November 1 through 4

Weather permitting on Friday, November 15 starting at 10:00 p.m., crews will remove the old signals and place new signals on the north side of 9000 South at 1510 West requiring the signals to be turned off. Short-term closures of the road are also expected lasting up to 30 minutes. Police officers will be directing traffic through 3:00 a.m.

Sidewalk replacement has started on the south side of 9000 South with crews starting near 900 West and working west. As crews replace individual driveway approaches and attached sidewalks, properties with more than one access will have one access closed while the other access is left open. Properties with only one access will be coordinated with the project team. 

Crews continue installing new traffic signal poles and street lighting conduit. 

*Schedule is subject to change due to weather, equipment, or material delays.

 

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographics as of August 1, 2024.

Built/Installed

Removals

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2024. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map.

This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 SouthDrivers should not drive into the work zone as hazards including significant drop-offs may be presentSee the detour map below.

River Oaks Driving Range Detour Route 

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 1, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the Redwood Road Renewed (9000 South - 6600 South) project by UDOT, click here.

To learn more about the Dominion Energy Gas Feeder Line 34 (1300 West from 7800 South to 11400 South), click here.