The project is coming to a quick close with all traffic lanes expected to be open on July 3 and full completion by July 31.

In time for the 4th of July Holiday weekend, all traffic lanes will be opened by the end of the day on Thursday, July 3. Thank you for your patience during this project!

Additional shoulder closures may be needed as crews finish the final pieces of work.

 

PROJECT UPDATES

Construction Activities June 26 - July 31

 

Know before you go! Check UDOT Traffic before hitting the road. 

Upcoming and Ongoing Activities

State Street to 700 West

The week of June 30, ADA pedestrian ramp work will start on the south side of 9000 South near 600 West. Patrons to the adjacent businesses should use the access from 700 West. This closure will last up to one week.

 

Remaing Activities 

Crews have nearly completed this massive road widening project. The following list of remaining items will be completed through July:

Sidewalks between 900 West and 700 West
Median curb between the Jordan River and 700 West and a section near 900 West
Work on the southeast corner of 9000 South Redwood Road
Installation of new street signs
Installation of grooved in lane lines (night work)
Landscaping
Final inspection and to do list
 

*Schedule is subject to change due to weather, equipment, or material delays.

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

 

Crews are completing the final pieces of landscaping through the end of July. Park strips feature water wise plantings and rock mulch.

Crews have completed all paving for this project and expect to finish lane striping by the end of the month. This project widened nearly 1.5 miles of road from two lanes in each direction to three.

 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Miscellaneous Information

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

complete
complete
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

live
live
End Construction: July 31, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the 9000 South Paving Project (Redwood Road to Bangerter Highway) by UDOT, click here.

To learn more about the State Street Paving Project (9400 South to I-215) by UDOT, click here.