PROJECT UPDATES
Construction Activities March 20 - March 30
Know before you go! Check UDOT Traffic before hitting the road.
Ongoing Activities
1300 West Sewer Line Work
Private utility lines are being installed for a new development south of 9000 South on 1300 West. This work is expected to take several weeks. Plan on delays and turning movement restrictions while work is taking place.
700 West to 900 West
Work continues on 700 West including upgraded storm drains, new asphalt, additional sidewalks, curb, and gutters. During this work, 700 West will be restricted to NORTHBOUND only. All southbound traffic will be detoured at Sandy Parkway. Local two-way traffic will be allowed between 8400 South and 8800 South. Click here for the detour map.
900 West to Redwood Road
As early as March 29 and 30, traffic on 9000 South between Redwood Road and 700 West will be shifted to the south side the road. This will provide crews space to reconstruct pedestrian ramps, repair concrete, and replace asphalt on the north side of 9000 South.
As early as March 31, the sidewalk on the north side of 9000 South will be closed while crews rebuild sections of the sidewalk. Please use the sidewalk on the south side of 9000 South as a detour route. Pedestrians should follow posted detour signs at closed sections.
As early as April 14, crews will begin removing asphalt on the north side of 9000 South starting at 700 West and working west toward Redwood Road. Business driveways, residential driveways, and side streets will remain open during the work except during a few specific activities:
- Asphalt removal
- Preparatory work to replace asphalt
- Asphalt placement
Work continues to install curb, gutter, and sidewalk on the north side of 9000 South between the Utah Islamic Center and the Rocky Mountain Power substation. Patrons to the Utah Islamic Center and adjacent office building may only enter from the business driveway to the west of the center.
Work continues on the southeast corner the the 9000 South Redwood Road intersection with a northbound lane closure and driveway access interruptions to the adjoining businesses. Drivers should plan on extra time through this area. This work will last through March 31 and patrons to the business complex should use accesses on Redwood Road or further east on 9000 South. See the map for additional information. See the map for alternate accesses.
Landscaping is being installed in the park strips on the south side of 9000 South between 1000 West and Redwood Road. Park strips will include drip irrigation and water-wise plantings.
Nearby residents and business may have an increase in noise, dust, and vibration as work takes place.
*Schedule is subject to change due to weather, equipment, or material delays.
Closures
Eastbound 9000 South left turn closed at 700 West
The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2025. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map. This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.
700 West is open for northbound traffic between 8800 South and 9000 South with local two-way traffic allowed between 8400 South and 8800 South. Click here for the detour map.
Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 South. Drivers should not drive into the work zone as hazards may be present. Click here for the detour map.
Transit and Traffic Information
UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information. |
Know before you go! Check UDOT Traffic before hitting the road.
Miscellaneous Information
Bridge Girder Placement
See the time lapse video of the crews placing the girders on 9000 South over the Jordan River.
Bridge Deck Concrete Pour
See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River.
Infographics as of December 31, 2024.
Did you know?
Our crews have used over 647,000 pounds of reinforced steel during this project - most on the new bridge over the Jordan River! That's more than a 747 weighs!
Contact Information
Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov
Schedule
Contact Information
To contact the Public information team with questions or concerns:
Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov
Stay Informed
To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line
Area Projects
To learn more about the 1300 West widening project by West Jordan City, click here.
To learn more about the 9000 South Paving Project (Redwood Road to Bangerter Highway) by UDOT, click here.