PROJECT UPDATES

 

Construction Activities May 22 - May 30

Ongoing Activities 

State Street to 700 West

A contractor for Dominion Energy continues work in this area through June. Please be aware of shifting work zones, lane closures, and night work. 

700 West to 900 West

Work continues on the outside lanes for the new bridge over the Jordan River. 

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 South. See the detour map below.

 River Oaks Driving Range Detour Route

900 West to 1300 West

The south leg of 1075 West will remain closed this week. Residents and patrons to the area businesses should use the detour shown. This closure is necessary due to a large buried underground wall and unknown utility lines in conflict with new water and storm drain lines. 

1075 West closure detour map

Water meter relocations continue on the south side of 9000 South requiring short-term water service interruption. This work will take place overnight with the sechedule as follows:

  • As early as Tuesday night May 28 (overnight) for residents between 1050 West and 1175 West.
  • As early as Thursday night May 30 (overnight) for residents and businesses between 1175 West and 1300 West.

Crews will notify individual property owners prior to any work taking place.

Work on block walls on the south side of 9000 South continues in this section. 

Work on the storm drain and water service lines may require short-term driveway access interruptions. Alternate business accesses are open and posted.

 

1300 West to Redwood Road

Through June, the south leg of 1510 West at 9000 South will experience temporary openings and closures lasting up to two weeks.

When 1510 West is closed, residents and businesses should use 9200 South at Redwood Road to access 1510 West. See the detour map for additional information.

1510 West closure detour map

Work on the storm drain and water service lines may require short-term driveway access interruptions. Alternate business accesses are open and posted.

*Schedule is subject to change due to weather, equipment, or material delays.

 

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographics as of May 1, 2024.

Built/Installed

9000 South Infographic of installations May 1, 2024

Removals

9000 South Infographic of removals May 1, 2024

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2024. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map.

This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 1, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the Redwood Road Renewed (9000 South - 6600 South) project by UDOT, click here.

To learn more about the Dominion Energy Gas Feeder Line 34 (1300 West from 7800 South to 11400 South), click here.