Construction Update | October 24, 2024

SR-204 (Wall Ave.) Bridge 

Upcoming Traffic Impacts

 

Final roadway striping activities on the bridge were completed this week. Crews are finalizing bridge abutment work and preparing for the final inspection.

 

Drivers can continue to expect heavy delays during peak travel times. We recommend using alternate routes if possible. Business access will be maintained.

 

The Ogden River Parkway trail is open. The trail will be narrowed to 4ft to accommodate project scaffolding. 

Pedestrian access on the east side of Wall Avenue between 18th Street and 20th Street is restricted and is an active construction zone at all times.

Work underneath the SR-204 bridge

SR-134 (4700 W.) Bridge

Crews will be performing final clean-up work at the SR-134 bridge for the next couple weeks. Drivers can expect minimal delays.

live
live
Construction Began (Spring 2024)

Work Hours: 7 a.m. – 5 p.m.

  • Occassional nighttime work 

Work Days: Monday - Friday 

  • Occassional weekend work 

planned
planned
Project Completion (Winter 2024)

Contact Information

The project team is here to assist, please call or email with any questions or concerns: 

Hotline: 855-740-8740

Email: webercountybridges@utah.gov

Stay Informed

Sign up for email updates by emailing webercountybridges@utah.gov with "Subscribe" in the subject line.

*Construction schedules are subject to change due to weather, utility, and material delays. 