Washington Boulevard Renewed

To preserve and extend the life of the pavement, the Utah Department of Transportation (UDOT) will conduct a project to resurface SR-235 (Washington Blvd) in North Ogden, between 400 North (North Street) and 2600 North. The project also includes replacing sidewalk pedestrian ramps, upgrading road signs, and installing a new concrete bus platform at the UTA bus stop located near the southwest corner of Washington Blvd and 2550 North.

Work began on May 1, 2023, and is expected to wrap up by the end of June 2023. 

*Schedules are subject to change due to weather conditions and material availability.

Schedule

live
live
Start Day Work: May 1, 2023

Sidewalk pedestrian ramp replacement, sign installation, etc.

Work hours: 7 AM to 5 PM

Work days: Monday through Friday

live
live
Start Night Work: May 8, 2023

Road work begins

Work hours: 7 PM to 5 AM

Work days: Sunday nights through Friday mornings

planned
planned
End Construction: Late-June 2023

Contact Information

To contact the public information team with questions or concerns:

Hotline: 877-495-4240

Email: udotregion1@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Washington Blvd Paving" in the subject line.