Project Activities*

 

  • The middle lanes between 1300 West and 1650 West have been paved and crews are paving the northern lanes between Pleasant Grove Boulevard and 1300 West through Saturday, July 19.
  • Beginning Sunday night, July 20, at 7 p.m. through 6 a.m., crews will work on installing storm drain under the road at Pleasant Grove Boulevard. This work will take place nightly through Wednesday morning, July 23, at 6 a.m. Once this work is completed at Pleasant Grove Boulevard they will move to 500 East the following week and work the same schedule at night.
  • Waterline installation along the north side of State Street east of 500 East is ongoing. Single lane closures will be used during this work and motorists can expect some delays.

 

 

*Dates are subject to change due to weather, equipment availability or other circumstances

 

 

 

 

New signals at Pleasant Grove Boulevard

 

Project Overview

The Utah Department of Transportation (UDOT) is widening US-89 (State Street) to a 7-lane section from 220 South in Pleasant Grove to 500 East in American Fork in two phases. The project will eliminate a choke-point by widening the road to three lanes in each direction to match existing sections on either end; upgrade signals at 500 East, 700 East, North County Boulevard, 1300 West, and Pleasant Grove Boulevard; add new curb, gutter, and sidewalk on the south side, add new storm drain, and add new/upgrade pedestrian ramps.

Phase 1:

The following intersections will be widened to help reduce congestion:

  • 500 East at State Street in American Fork in 2025. 
  • Pleasant Grove Boulevard at State Street in 2025. 
  • 1650 West to 1300 West in 2025
  • State Street will receive a new pavement layer between the intersections.
  • Construction in this phase is anticipated to finish in October 2025.

 

Phase 2:

  • Phase 2 from 1650 West in Pleasant Grove to 600 East in American Fork is currenlty in design with construction planned in 2026. 1300 West will be widened during phase 2.

500 East/State Street Intersection

Pleasant Grove Boulevard/State Street Intersection

 

complete
complete
State Street Pavement Rehabilitation

Complete

complete
complete
Pleasant Grove and North County Boulevard Intersection

Complete

live
live
State Street and Pleasant Grove Boulevard Intersection

Construction will begin February 27, 2024

live
live
State Street/500 East Intersection

Construction will begin in late February 2024.

live
live
SR-74 (100 East) Deep Curb Replacement

Construction starts April 14

Stay Informed: Sign up for email updates to stay informed about impacts that could affect your travel at afpgimprovements@utah.gov. Or, reach out to the team for questions or concerns at 888-556-0232.