Project logo SR-153 | Beaver Canyon Corridor | Reconstruction

Project logo SR-153 | Beaver Canyon Corridor | Reconstruction

UDOT is completing emergency repairs on approximately 17 miles of State Route 153 in Beaver Canyon in response to damage caused by a combination of wildfires and flooding.

Overview

Property Owner Access Update:

Piloted access between Beaver and Kents Lake Road is closed for the season and is expected to resume in spring 2027. See the Property Owner Access tab for more details. 

Project Timeline

Crews will close SR-153 and pause construction for the winter. Snow, freezing temperatures, and elevated risks make conditions in the canyon unsafe for crews.

During the winter, the project team will evaluate the damage, identify necessary improvements, and develop detailed plans for permanent reconstruction of SR-153.  

SR-153 will remain closed to general public travel through 2027. Limited, piloted access to Kents Lake Road is expected to resume in spring 2027, as conditions allow. Our goal is to reopen SR-153 in fall 2028, although the timeline may change as we learn more about the repairs and the impacts of spring runoff.

Project Overview

The Utah Department of Transportation (UDOT) is conducting emergency work on approximately 17 miles of State Route 153 in Beaver Canyon following significant damage caused by flooding and runoff from the Beaver Mountain Fire burn scar.

Several sections of SR-153 have been severely damaged, including areas where portions of the roadway have washed away or been significantly undermined. The full extent of the damage is still being evaluated, and additional damage may occur as rain and runoff continue.

UDOT has closed SR-153 with gates at approximately Milepost 3.5 and Milepost 14.5 to restrict access to the affected area. The closure is necessary because conditions in the canyon remain hazardous, with multiple risks to the public, including unstable roadway, ongoing runoff, damaged infrastructure, and active fire-related hazards. Construction activities and heavy equipment will also be operating within the project area.

The public is prohibited from entering the closed area or bypassing the gates. The closure will remain in place to protect the public and construction crews while emergency work is underway.

UDOT and its construction partners are working to evaluate the damage, stabilize critical areas, restore limited access where possible, and develop permanent repairs. The timing and extent of the repairs will depend on site conditions, continued damage, design requirements, and other factors.

The situation is continuing to develop. UDOT will update this website regularly as conditions change and additional information becomes available.

 

Map of SR 153 through Beaver Canyon. UDOT PIN 23714

 

Documented Damage

UDOT visited the area to assess damage in July. Below is a video clip from the drone footage shot during the visit.

 

Project Timeline

live
live

Fall 2026 - Winter 2026/2027

  • UDOT continues to assess damage and develop the scope and design for permanent repairs.

  • Crews will close SR-153 and pause construction for the winter.

  • UDOT is working to establish safe, temporary unpaved access for property owners and other authorized users in the canyon. This access will be controlled and will not reopen SR-153 to general public traffic.

planned
planned

Spring 2027

  • UDOT will develop and construct a permanent solution for SR-153, including roadway reconstruction and resilient engineering measures designed to address damage from the flooding and reduce the risk of future post-fire impacts. 
  • Major reconstruction is anticipated to begin Spring 2027.

complete
complete

Project Milestones

  • July 2026: UDOT initiated the project with $350,000 in emergency funding.
  • Aug. 12, 2026: UDOT issued a Progressive Design-Build (PDB) solicitation and selected the project contractor team.
  • Aug. 2026: The Utah Transportation Commission approved an additional $50 million in initial funding for the project at their Aug. 14 meeting. 
  • Aug. 2026: UDOT issued Notice to Proceed to Ralph L. Wadsworth Construction Company. 
  • Oct. 2026: Crews begin offering piloted access from Beaver to Kents Lake Road for property owners and authorized users. 
  • Nov. 2026: UDOT pauses piloted access and begins a winter shutdown. 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-254-7357

Email: sr153beavercanyon@utah.gov

Stay Informed

To receive project update emails, please contact the public information team at the email address above and enter "Project Updates" in the subject line.