Project Updates
Heads up | Closure on Northbound Highway-89 at the SR-126 Intersection
Northbound US-89 at the 2000 W (SR-126) junction will close to through traffic from Monday, May 19, to Thursday, May 22. Drivers should follow the posted detour route and plan for delays. Please refer to the map below for more information.
As early as Tuesday, April 15, 2025, the Utah Department of Transportation (UDOT) will begin construction on US-89 from the US-89/SR-126 intersection to just south of Hargis Hill Road in Willard. The project improvements include:
- Full depth roadway reconstruction to extend the life of the road including consistent shoulder-widths through the project
- Repairing and improving drainage systems to prevent pooling and road deterioration
- Installing a storm drain system on 750 North (SR-315) from US-89 to I-15
- Modifying and replacing select driveways, parking lots, and landscape features
- Improving roadside barriers and pedestrian ramps
- Upgrading and relocating existing utilities
Work on the project will occur Monday through Saturday between 7 a.m. and 7 p.m. The project is scheduled to be completed as early as Fall 2026. Construction dates are approximate and subject to change
What to Expect During Construction
- Increased noise and vibration
- Reduced and shifted lanes on US-89
- Speed limit reductions in areas of active work
- Temporary neighborhood and driveway access changes
- Intermittent night and Sunday work.
Overview
UDOT will construct improvements along US-89 from the US-89/SR-126 intersection to just south of Hargis Hill Road in Willard. These improvements will replace subgrade material (e.g., compacted gravel) and pavement which has reached its operational expectancy and become unstable. Additionally, much of the existing drainage along this section of US-89 will be upgraded to avoid pooling and roadway storm runoff (i.e., sheet flow) during stormy weather. This will extend the lifetime of the road, while creating a safer, more comfortable road for drivers.
Project Area
For questions or to be added to the project email update list, please contact us at:
- Phone: 480-903-4838
- Email: US89Willard@utah.gov
Stay Informed
Subscribe to our email newsletter to receive project updates. Complete the form on the Contact Us page or email us89willard@utah.gov with Project Updates in the subject line.
Nearby Projects
State Route 13 Paving (Brigham Main Street)
Hotline: 800-292-3557
Email: SR13paving@utah.gov
Website: SR-13 Paving - PublicInput