Overview

Project Overview

The Utah Department of Transportation (UDOT) will be performing road preservation work along US-89 from 22nd Street to 2nd Street and along SR-235 from 2nd Street to North Street in Weber County. This project is designed to extend the life of the road and improve safety.

Construction is scheduled to take place from June 21, 2026, through mid-October.  Work will primarily occur during nighttime hours to minimize daytime traffic impacts, with a six-week stint of daytime work required for sidewalk ramp improvements.

Key Features Include:

  • Pavement repair and resurfacing
  • Concrete panel replacement and road rehabilitation
  • ADA upgrades, including reconstruction of pedestrian ramps
  • Traffic signal improvements at key intersections
  • New pavement markings, striping, and signage
  • Curb, gutter, and sidewalk improvements
  • Minor landscaping and irrigation restoration

*See Impacts & Updates tab for more information and details

Map of US-89 Washington Blvd Concrete Panels Paving Project Route

Map of Project Area

Stay Informed

To receive occasional construction email updates, please enter your information below:

Contact Information

To contact the public information team with questions or concerns:

801-838-8361

us89washingtonboulevard@utah.gov

 

Stay Informed

To receive email updates, please fill out the form at the end of the Overview page (or) email the public information team at and type "Updates" in the subject line.

Active Construction

Hours: Night and Day Work

  • Nighttime Work: 8 p.m. - 6 a.m. 
  • Daytime Work: 7 a.m. - 5 a.m.

Workdays: Sunday Night - Friday Morning

No work on Saturdays or holidays

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

planned
planned

Construction Phase: Jun 21 - Oct 2026

06/21/26: Work begins at the job site and initial mobilization activities take place.

  • Daytime work: Sidewalk deconstruction begins, with sidewalks and shoulders closed in active work areas.
  • Nighttime Work: Road reconstruction begins, including roadway removal and replacement activities.

planned
planned

Weekly Traffic Impacts: 06/22 - 06/26

During Nighttime Construction Hours:

  • Two lanes will be closed in both directions overnight, with traffic guided by barrels and signage.

One lane will remain open at all times in both directions.

  • Noise should be expected as crews are replacing the panels in the road.

During Daytime Construction:

  • All regular operative lanes will be open as crews work on the shoulder/sidewalks in the area.
  • Turn lanes may be used for equipment—watch for barrels and signage.

planned
planned

Project Milestones

06/21/26: Work in project area begins