This project is complete. We would like to thank you for your patience and cooperation during construction, and invite you to send any feedback, questions, or concerns regarding this project to our team using the contact information found in the sidebar.


Project Background

UDOT conducted a project to renew US-89 from Wall Avenue to 2700 North. The project entailed removing and replacing the top layer of asphalt, along with installing new pedestrian ramps to meet current ADA standards, new curb and gutter, and updated road signs. 

This project extended the life of the existing pavement, while providing a smoother driving experience for motorists along this corridor.

Map highlighting US-89 between 2700 North and Wall Avenue to show the construction area

Work began on May 13, 2024 and concluded in early November 2024.

Schedule

complete
complete
Concrete Work: May to Mid-June 2024

complete
complete
Project Suspension: Mid-June to mid-August 2024

Suspending work to allow an ongoing development project within our work zone time to install a sewer connection into US-89

complete
complete
Paving Work: August to Early October 2024

Contact Information

To contact the public information team with questions or concerns:

Hotline: 877-495-4240

Email: udotregion1@utah.gov