UDOT is conducting a project to renew US-89 from Wall Avenue to 2700 North. The project entails removing and replacing the top layer of asphalt, along with installing new pedestrian ramps to meet current ADA standards, new curb and gutter, and updated roadway signs. 

This project will preserve and extend the life of the pavement, while providing a smoother driving experience for motorists along this corridor.

To sign up for construction updates, send us an email with "US-89 Renewed" in the subject line.

Map highlighting US-89 between 2700 North and Wall Avenue to show the construction area

Schedule

complete
complete
Concrete Work: May to Mid-June 2024

Work will take place up to seven days a week, both day and night. However, in order to reduce impacts to traffic, work affecting the roadway will be done at night, between the hours of 7 p.m. and 8 a.m.

Nearby residents should expect an increase of noise and vibration at night.

Schedules are subject to change due to weather conditions and material availability.

live
live
Project Suspension: Mid-June to Late-July 2024

Suspending work to allow an ongoing development project within our work zone time to install a sewer connection into US-89

planned
planned
Paving Work: Late-July to Late-September 2024

Work will take place up to seven days a week, both day and night. However, in order to reduce impacts to traffic, work affecting the roadway will be done at night, between the hours of 7 p.m. and 8 a.m.

Nearby residents should expect an increase of noise and vibration at night once paving activities begin.

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 877-495-4240

Email: udotregion1@utah.gov

Stay Informed

To receive weekly construction updates via email, please contact the public information team at the email address above and enter "US-89 Renewed" in the subject line.