Construction Update | October 3, 2025

Last week crews completed guardrail installation.

In the coming weeks, crews will finish minor clean up throughout the corridor and be back to finish the final coat of striping in approximately 2-weeks.

Blue sky and a hilly background with pinetrees. In the foreground there is a construction working working on guardrail installation and replacement with an orange long sleeve high visibility shirt and a white hardhat. Black recently paved roadway is also visible in the foreground of the photo.

 

 

Final guardrail installation. 

Schedule

Work Hours: 7 a.m. - 7 p.m.

Workdays: Monday - Thursday

Intermittent Overnight Closures

*Construction schedules are subject to change due to weather, utility and material delays.

live
live
Construction (Summer 2025)

One-way flagging operations, Monday - Thursday, 7 a.m. – 7 p.m. 

planned
planned
Project Completion (Fall 2025)

complete
complete
Project Milestones

Construction Began Wednesday, July 16, 2025

Final Design (2024)

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-996-7086

Email: us89beavercreek@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.