Skip Navigation
 

US-89 | 2nd St. to Wall Ave. | Harrisville Rd. | Improved

US-89 | 2nd St. to Wall Ave. | Harrisville Rd. | Improved

The Utah Department of Transportation (UDOT) will be performing roadway preservation work along 2nd Street to Wall Avenue along US-89 in Weber County. This project is designed to extend the life of the roadway and improve safety for all users.

Overview

Construction Complete

This project was completed on September 25, 2026.

Questions?

UDOT Region 1 office 801-620-1600
Mon - Fri, 8:00 a.m. - 5:00 p.m.

Project Overview

The Utah Department of Transportation (UDOT) resurfaced US-89 in Weber County from 2nd Street to Wall Avenue. The project helped preserve the life of the road and enhanced motorist safety by providing a smoother driving surface. Additional work included ADA sidewalk ramp upgrades and restriping throughout the project area.

Construction began on August 3 and was completed in early October. *All project work is now complete.

Crews began daytime work on North Street, then moved northwest to Wall Avenue before completing the ramps between 2nd Street and North Street. Multiple ramps were worked on simultaneously. *All daytime and nighttime work is now complete.

Nighttime work began near Wall Avenue and progressed south toward 2nd Street. Crews made several passes through the corridor to complete the work.

On-street parking was restricted during construction hours for the duration of the project. These restrictions have ended.

*See the Impacts & Updates tab for more information and details.

Map of Project Area

Map of Project Area

Project Timeline

complete
complete

Active

THIS PROJECT IS COMPLETE

planned
planned

Completed Milestones

08/03/26: Work in project area began

08/07/26: Pedramp/daytime work is completed

08/29/26: Work break commenced

09/08/26: Work break ended

09/25/26: Crews finished all outstanding work items