Overview

<-- Return to Juab County Projects

 

Construction Complete

This project was completed on July 10, 2026.

Questions?

UDOT Region 3 office 801-227-8000
Mon - Fri, 8:00 a.m. - 5:00 p.m.

 

Project Overview

The Utah Department of Transportation (UDOT) resurfaced sections of U.S. Highway 6 and State Route 36 from Elberta to Lynndyl in Juab County. The project objectives were aimed at preserving the life of the road. This resurfacing process helped increase the longevity of the road surface, address road imperfections, and enhance motorist safety by providing good skid resistance for vehicles. Additional work included crack sealing, rumble strips, updated signage, and refreshed line striping.

Project Map

 

Map of the US 6 and SR 36 Improved project showing the construction areas from Elberta to Lynndyl on US-6 and a small section of SR-36 to the Tooele County Line

Map of Project Area

Paving Operations on US-6

US-6 Paving Operations | Near Mile Post 145 | 05/05/2026

Schedule

Work Hours: Sunrise to Sunset

Workdays: Monday - Friday

All lanes remain open on weekends and holidays.

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

This Project is Complete

  • This job is substantially complete as of July 10, 2026.

complete
complete

Project Milestones

  • Phase 1 Construction complete: Oct. 27, 2025 - Nov. 14, 2025
    • Crews sealed road cracks to protect the pavement during winter months before the full resurfacing scheduled for Spring 2026.
  • Phase 2 Construction complete: April 22, 2026 - July 10, 2026 
    • Paving Operations Complete - Full resurfacing of US-6 from Elberta to Lynndyl and SR-36 to Tooele County Line.
    • Upgraded signage and refreshed line striping also added.