US-40 | Currant Creek to SR-208 | Fruitland | Renewed
US-40 | Currant Creek to SR-208 | Fruitland | Renewed
The Utah Department of Transportation (UDOT) will repave a 1-mile section of U.S. Highway 40 near the Wasatch and Duchesne County line as well as a 7-mile section between Fruitland and SR-208. Roadway reconstruction will be conducted near Red Creek (MP 65), then mill the asphalt and pave US-40. Following paving activities, reinstallation of barriers and guardrail and pavement markings and signage will be replaced.
Project Overview
The Utah Department of Transportation (UDOT) is repaving a 1-mile section of U.S. Highway 40 near the Wasatch and Duchesne County line as well as a 7-mile section between Fruitland and SR-208.
Work began the week of July 6th. We will conduct roadway reconstruction near Red Creek (MP 65), then mill the asphalt and pave US-40. Following paving activities, we will reinstall barriers and guardrail and replace pavement markings and signage.
Work is anticipated to be completed by late November 2026.
Project Map
Current Construction Activities: September 2026
Crews are conducting roadway reconstruction and paving at Red Creek (between MP 65-65.7).
- While reconstruction and paving is underway near Red Creek, US-40 is narrowed to one-way traffic with a 12-foot-wide lane during daytime and nighttime hours as well as on weekends, directed by flaggers or temporary signals. Expect delays.
- While paving occurs between Monday, September 21 and approximately Wednesday, September 30, drivers should anticipate 2-3 hours closures of side streets (including Red Creek Road/41950 West) while paving equipment passes by and the new asphalt cures.
Schedule
- Live – Construction: July 2026 – November 2026
Work will begin in early July 2026 and is anticipated to be complete late-November 2026.
- Planned – Project Completion
The project is anticipated to be complete late-November 2026.
Contact the Team
Hotline: 435-352-6068
Email: us40renewed@utah.gov
Web: udotinput.utah.gov/us40renewed
Stay Informed
To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.