Overview

U.S. Route 40 Culvert Maintenance

Work has begun to repair multiple culverts along US-40 in Summit County that have deteriorated due to corrosion from sediment and debris-laden flood waters. These repairs will increase drainage function and improve roadway safety. Maintaining the roadway drainage system is critical to the long-term structural integrity of the highway system.

Work was pause for the winter, and will resume in early summer of 2026.

Road shoulders along US-40 may be closed during work hours in the highlighted area shown in the map below. 


Work includes lining and repairing the culverts, replacing storm drain infrastructure and grading the median to accommodate the drainage flow.

Construction began August 11, 2025.

 

Examples of deteriorated culverts in need of replacement under US-40. 

Schedule

Project Timeline

live
live

Construction: August 2025 - July 2026

Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday, Saturdays as needed

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-925-2801 (project code: 11602)

Email: us40culvert@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.