U.S. Route 40 from SR-248 to the Wasatch County Line - Work is Complete 

The Utah Department of Transportation (UDOT) improved the concrete pavement on U.S. Route 40 (US-40) from SR-248 to the Wasatch county lines. The improvements included filling cracks, replacing concrete slabs as needed, and improving bridge joints. Crews also improved striping, signs and cameras as needed throughout the project area. 

Work is underway and will be substantially complete by August 28, 2023.  

 

Schedule

complete
complete
Design: Spring 2022 to Fall 2022

complete
complete
Construction: May 15, 2023 through August 28, 2023

Work Hours: 5 a.m. - 7 p.m. with some night work possible. 

Workdays: Monday through Sunday

Schedules are subject to change due to weather conditions and material availability.

 

Stay Informed

To receive weekly construction updated, please contact the public information team at the email noted under contact information  and enter "Weekly Updates" in the subject line.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-200-4670

Email:  us40-248towasatchcounty@utah.gov