Project Overview

As early as March 2, 2026, UDOT will begin a project along approximately nine miles of US-191 to preserve and extend the life of the pavement by placing a chip seal road treatment (see map).


This project also includes safety improvements like guardrail installation and sign replacements along the construction route.

Project Map

Project Timeline

Construction will take approximately 3 months to complete.

March 2, 2026: Crews will begin a crack seal along the construction route. 

Late March to May 2026: Crews will place a chip seal road treatment, install guardrail, and replace signage along the route. 

 

Schedule

Work Hours: 7 a.m. - 6 p.m.

Workdays: Monday - Friday

Weekend work may take place as needed.

Schedules are subject to change due to weather conditions and material availability.

live
live
Spring 2026 - Early Summer 2026

In early March, crews will begin work by sealing cracks in the asphalt north and south of the new alignment of US-191 in this area. 

Once temperatures warmer in the spring, they will return to place a chip seal, replace guardrail, and improve signage. 

live
live
Project Milestones

Crews began the crack seal on March 2, 2026.