Project Overview

We are adding two more travel lanes on U.S. Highway 189 (US-189) between Wallsburg and Charleston to reduce congestion and increase safety for drivers. This is the last stretch of US-189 in this area with only one lane each way. When finished, US-189 will have two travel lanes in each direction from Provo to Heber City.

 

The main focus of the project is building the new travel lanes into the eastern hillside as a separate and elevated road, known as a split highway, similar to sections of US-189 in Provo Canyon. An example of what the split highway could look like when finished is shown below.

Other key features being built with this project include:

  • New traffic signal at the intersection of US-189 and SR-113

  • Improved access and parking at the Island Beach Day Use Area, including longer acceleration and deceleration lanes and a new parking lot

  • Better sight lines through the curved section along US-189

  • New wildlife fencing to protect drivers and animals

Construction started in October 2025 and is expected to wrap up in the fall 2027. 

 

US-189 Existing and Split Highway Visualization

 

US-189 Wallsburg to Charleston Construction Area Map

Schedule

*Schedules outlined below are subject to change due to weather conditions and material availability.

live
live
Active Construction

New Northbound Lanes (Fall 2025 – Summer 2026)

  • Install rockfall protection fencing 
  • Blasting and hillside excavation, and road grading
  • Install wildlife fencing 
  • Paving operations

Island Beach Area Undercrossing (Fall 2025 – Summer 2026)

  • The Lake House Restaurant at Deer Creek remains open during construction
  • Traffic shifted to temporary bypass lanes
  • Construct future parking lot
  • Construct pedestrian undercrossing

SR-113 & US-189 Intersection (Early 2026 – Summer 2026)

  • Build new road alignment
  • Install new traffic signal and complete intersection improvements

planned
planned
Upcoming Construction

Southbound Lanes Reconstruction (Fall 2026 – Summer 2027)

  • Shift all traffic to new northbound lanes

  • Improve sight distance through curved sections of US-189 

  • Replace pavement 

  • Improve access and parking at Island Beach Day Use Area, including extended acceleration and deceleration lanes 

complete
complete
Project Milestones

  • First Phase of Controlled Blasting and weekly closures (Early Winter 2026)

  • Project advertised and contractor selected (Summer 2025)

  • Final design and construction plans (Fall 2021 – Spring 2025)

  • Environmental analysis and documentation (Fall 2021 – Spring 2024)

  • Public hearing and comment period (Spring 2024)

    Contact Information

    To contact the public information team with questions or concerns: