Project Description

The Utah Department of Transportation (UDOT) will be implementing safety enhancements within Ogden Canyon during the Summer of 2024. The first objective is to install centerline sinusodial rumble strips from milepost MP 9.0 to 13.9. The second objective is to replace and upgrade concrete barriers with base rock wall cap reinforcements from MP 9.0 - 9.9 (see map below).  Refreshed lane and roadway painting/striping will be applied following the work.   

 

Latest Notice (10/20/24): Crews will return during Spring 2025 to apply a chip seal on the westbound lanes from Mile Post 9 - 9.9.

 

Schedule

live
live
Construction Start: August 15, 2024

Work Hours: 7am - 5pm | Includes up to 8 nighttime canyon closures

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

planned
planned
Construction End: October 5, 2024

Estimated duration of the project is 75 calendar days, which includes repaving the road that was impacted during paving. Please check back for additional details on progress.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8361

Email: sr39updates@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.