Overview

This project was completed on September 22, 2025.

For questions or more information, contact UDOT's Region 3 office at 801-227-8000 Monday - Friday 8 a.m. - 5 p.m.

 

Project Description:

The Utah Department of Transportation (UDOT) resurfaced the road on SR-150 from Trial Lake to Sulphur Campground. The project objectives were aimed at preserving the life of the road. This resurfacing process helped increase the longevity of the road surface, addressed road imperfections, and enhanced motorist safety by providing good skid resistance for vehicles. Additional work included refreshed lane and road painting/striping, as well as updated roadside signage.

 
 

Construction truck applying fresh road surface treatment on a SR-150 near Trial Lake..                            SR-150 turn to Trial Lake| 081325

Map showing the construction area of SR-150 from Trial Lake to Sulphur Campground. The textbox reads, "Roadway resurfacing in both directions."

Stay Informed

To receive occasional construction email updates, please enter your information below:

Project Timeline

complete
complete

This Project Is Complete

complete
complete

Project Milestones

  • Work hours were daytime (7 a.m. – 8 p.m.).

  • Workdays were Monday – Friday.

  • July 14: Construction started.

  • July 21: Paving operations began.

  • September 2 – 16: Installation of roadside delineator posts and travel lane painting and striping were completed.

  • September 22: Construction ended.