This Utah Department of Transportation (UDOT) project will repave State Street (US-89) between 3000 South in South Salt Lake and 400 South in Salt Lake City, extending pavement life and improving safety along this important route.

Below is an outline of upcoming work:

REMINDER: On-street parking will be restricted while this project is underway. Any vehicles parked on the shoulder may be towed.

Segment 1: 3000 South to 1700 South

  • Nighttime milling and paving along State Street are scheduled to be complete tonight (July 10) with the exception of the area near the UTA S-Line at 2200 South.
  • Expect some intermittent lane closures and delays starting July 26th as crews raise utilities and complete final striping during evening hours in July and August.
    • During this work, residents and businesses should expect noise and vibrations.

Segment 2: 1700 South to 400 South

  • Nighttime milling and paving along State Street have begun in this section. Crews will work to mill and pave turn lanes and intersections, so expect some side street closures during nighttime hours for the next two weeks to accommodate work. Please use alternate routes while closures are in place.
    • Crews plan to conduct milling and paving work between 1700 South and 750 South first and are scheduled to be complete by mid-August.

Daytime and nighttime work will occur daily. Nighttime work will occur between 7:00 pm and 6:00 am.

image.png

______________________________________________________________________

What to Expect During Construction:           

Vehicles:

  • While nighttime work is underway, State Street may be restricted down to one lane in each direction. Drivers are asked to slow down in the work zone and plan for minor delays.
  • During daytime hours, drivers should expect minor delays as lane closures will occur to accommodate the utility work.
  • Side street and business accesses will remain open during work except for brief periods of time when milling and paving operations are underway and when equipment passes directly in front of them.
  • On-street parking will be restricted while this project is underway. Any vehicles parked on the shoulder may be towed.
  • Following milling operations, loose gravel can be expected. Please reduce speeds and increase distance to avoid gravel damage to vehicles.
  • Car dealerships should move vehicles back from the front of the lot to avoid damage from gravel and debris.
  • Motorcycles should use extra caution when driving on the milled surfaces and watch for any uneven pavement.

Cyclists:

  • Cyclists should anticipate shoulder closures along State Street at any time during this project. Please use alternate routes until work is complete and traffic control devices are removed.

Transit:

  • Bus routes along State Street will be temporarily impacted while work is underway. Please see posted signage for route adjustments.
  • When crews conduct work where the UTA S-Line crosses State Street, additional lane closures may be needed, and trail detour routes will be in place. More details will be provided as this work approaches.

For real-time traffic information, visit udottraffic.utah.gov or download the app.

 

Questions? Contact the Public Information Team:

HOTLINE: 385-509-2035   

EMAIL: statestslcpaving@utah.gov   

WEB: udotinput.utah.gov/statestslcpaving

 

Contact Information

For questions regarding the project, please contact the Public Information Team:

Hotline: 385-509-2035