Latest Upate [07/11] : Crews are working this weekend, July 11 - 13 in order to finish main travel lane paving operations. See 'Impacts & Updates' tab for more information.

 

Project Description:

The Utah Department of Transportation (UDOT) will resurface State Street (SR-186) from North Temple to 400 S in Salt Lake County. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface, address road imperfections and enhance motorist safety by providing a smoother, more durable road. Additional work includes upgraded pedestrian ramps to meet ADA compliance, refreshed lane painting/striping.

Pedestrian ramp ADA upgrades on 300 S State Street

Pedestrian ramp ADA upgrades | 300 S State Street | 06/18/25

Construction map of work zone on State Street

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

live
live
Construction Start: June 2nd

Work Hours: Night Work (7pm - 6am)

Workdays: Monday - Friday; Sat. and Sun. as needed

 

June: Pedestrian ramp rebuilds for ADA compliance; Lower utility covers

July: Paving operations begin as early as June 30

  • July 11 - 12: Crews are working Saturday night - Sunday morning

Schedules are subject to change due to weather conditions and material availability.

planned
planned
Construction End: August 2025