Project Overview

The Utah Department of Transportation (UDOT), in partnership with the Capitol Preservation Board (CPB) and the Utah Division of Facilities Construction and Management (DFCM), built a new, single-lane roundabout at State Street and 300 North in Salt Lake City, in front of the Utah State Capitol building. 

The roundabout is designed to enhance safety at this busy intersection for all users.

In coordination with the roundabout project, the DFCM relocated the State of Utah wall to allow more space for gatherings and photography opportunities. These efforts combine to create a welcoming environment for residents and Capitol visitors. 

 

Rendering is conceptual for visualization purposes only and may not be an exact replica of project plans. Developed by MGB+A.

Schedule

complete
complete
Sept. 23, 2024

Construction begins. 

Schedules are subject to change due to weather conditions and material availability.

complete
complete
Jan. 6, 2025

Intersection opens to all users.

Schedules are subject to change due to weather conditions and material availability.

live
live
Spring 2025

Final pavement treatments and landscaping.

Schedules are subject to change due to weather conditions and material availability.

complete
complete
May 17, 2025

Intersection closes from 6:30 a.m. to 5 p.m. for pavement treatments. 

Schedules are subject to change due to weather conditions and material availability. 

planned
planned
May 31–June 1, 2025

Intersection closes from 6:30 a.m. to 5 p.m. for road striping. 

Schedules are subject to change due to weather conditions and material availability.

Contact Information

Hotline: 385-800-7003