SR-198 | 12000 S. Payson | Improved

SR-198 | 12000 S. Payson | Improved

Upgrades at SR‑198 and 12000 South added protected left turns, realigned lanes, and reduced congestion, improving safety and creating smoother, more efficient travel.

Overview

Construction Complete

This project was completed in September 2026.

Questions?

UDOT Region 1 office 801-620-1600
Mon - Fri, 8:00 a.m. - 5:00 p.m.

Project Overview

The SR-198 and 12000 South Intersection Improvement Project will add protected left-turn pockets from SR-198 (State Street) to 12000 South, and also aligned the lanes along 12000 South across the intersection near Payson. The goal of this project was to enhance safety and traffic flow at this intersection.

 

Project Map

Map highlighting intersection improvements in orange where State St (SR-198) meets 12000 S, on the border of Payson and Spring Lake.

 

Benefits

  • Enhanced safety for drivers making left turns
  • Inhibits turning vehicles from impeding traffic flow along SR-198 at this intersection
  • Improves sight line visibility for vehicles turning onto or crossing SR-198

Project Timeline

live
live

Construction Complete

Construction for this project has concluded.

complete
complete

Design

Construction: August 2026 - September 2026

Design: Fall 2024 - Early 2025