SR-9 Improved
SR-9 Improved
UPDATE: October 7 - 11
On Monday and Tuesday, there will be rolling, one lane operations as crews use a profilograph machine to grind off any high spots on the road to create a smooth driving surface. These rolling closures will delay traffic for no more than 15 minutes in each direction.
Wednesday through Friday of this week, there will be changing traffic patterns with no single lane operations. Traffic will be shifted around active construction as crews work on finishing upgrades to the project.
Substantial completion of the project will be October 17, 2024*.
Thank you for your patience.
Project Hotline/Text: 435-531-1358 or Email: sr9paving@utah.gov
Webpage: http://udotinput.utah.gov/sr9paving
*Schedule is subject to weather and other unforeseen circumstances.
The Utah Department of Transportation (UDOT) started improvements to SR-9 near Virgin, UT and Rockville, UT on Monday, July 15, 2024. This work will improve safety through the corridor, upgrade the asphalt surface and enhance the durability of the roadway. Improvements include:
- Asphalt removal and replacement - MP 19 to MP 21 near Virgin a)d MP 22 to MP 25 near Rockville from July 15 to August 7, 2024. Traffic patterns will be changing during this time.*
- Guardrail safety improvements in designated areas - August 2 to mid-September 2024.*
- Rockville Bridge Rehabilitation - August 2024.*
- New rumble strips, sign posts and pavement marking paint - September to October 2024.*
It is anticpated the project will be completed by mid-October 2024.
*Schedule is subject to weather and other unforeseen circumstances.
Map shows milepost (MP) locations on SR-9. This project will improve from approximately MP 19 to MP 21 and MP 22 - 25.
Schedule
Contact Information
To contact the public information team with questions or concerns:
Hotline: 435-531-1358
Email: sr9paving@utah.gov
Stay Informed
For up-to-date information, please check this site often.