2022 Construction Schedule

Estimated Start Date:   Wednesday, June 20

Construction Days:  Mon. - Fri. (Sat. only as necessary); No holidays

Construction Times:  7am - 7pm

Estimated Completion Date:  September

 

Note: Schedules are subject to change due to weather and materials available

 

Last Updated: 8/4/22

Forecast Work Details:

 

August 8 - 12

  • Roadway messaging paint lines, delineators and various roadway directional sign installations will begin
  • First coat of travel lane paint lines will be applied along entire route

August 15 - 19

  • Roadway directional sign installations will continue

By Early September

  • Second coat of travel lane paint lines will be applied along entire route

 

For Real-Time Traffic Information Please Visit:   https://udottraffic.utah.gov/

 

Image: Chip Application and Fog Seal Coat Complete; MP 11 Looking North; 08/3/22

 

 

Safety Notice:

For your safety, as well as the safety of the working in the area, please use extra caution and stay alert while driving through construction zones.  Businesses and residents in the area should anticipate increased noise, dust, and vibration associated with construction.


 

 

UDOT PROJECT INFORMATION PAGE


LATEST TRAFFIC CONDITIONS

udottraffic.utah.gov 

or download the latest UDOT Traffic App.


FOR IMMEDIATE PROJECT INQUIRIES

Jeffrey Putzke, Public Involvement Manager

Phone:  801-652-4008

Email:  jeffputzke@utah.gov


OTHER NEARBY UDOT PROJECTS

S.R. 208 Duchesne County Project [ CLICK HERE ]