Project Description

The Utah Department of Transportation (UDOT) will resurface State Route 77 in Utah County from Main Street in West Springville City to SR-147 near the Lakeshore community. The project objectives are aimed at preserving the life of the roadway. This resurfacing process will help increase the longevity of the road surface, address roadway imperfections and enhance motorist safety by providing good skid resistance for vehicles. Additional work will include updated roadway signage, travel lane painting/striping, and road surface directional markings.

Route:  SR-77 / Start Milepost: 0 - End Milepost: 6.7

 

SR-77 Lakeshore | Chip & Seal Paving Process | 8/19/24

 

SR-77 Looking East | Paving and Temporary Paint | 6/06/24

 

SR-77 | West Springville City to Lakeshore Paver Photo

SR-77 Looking East | 1.5 Inch Hot-Mix-Asphalt Paving | 5/16/24

 

SR77 Paving Map

Documents

*Schedule

Work Hours:  7am - 7pm

Work Days:  Mon - Fri (Sat. as necessary)

*Schedules are subject to change due to weather conditions and material availability.

-------------------------------

Total project duration will be approximately 2 months. Please check back for additional details on progress.

complete
complete
Phase 1: May 6 - June 7

  • Intersection and property access paving/gravel applications (near completion)
  • Paving application along entire route.

Tuesday, May 28 - Friday, June 7

  • Gravel material added to smooth edge of asphalt to the shoulders (shouldering).
  • New/Upgraded roadside sign installations
  • Temporary travel lane striping

This entire phase will take approximately 1 month to complete

complete
complete
Phase 2: August 19 - 28

  • Chip-Seal coat resurfacing. Primarily from Palmyra Dr.. to SR-147.  

!! Expect lane width restrictions !!

  • Permanent travel lane, roadway directional painting and striping
  • Miscellaneous work TBA

The resurfacing work should take just over 1 week to complete, with additional work continuing for an additional 5 days.

planned
planned
East-side Paving: Spring 2025

Due to ongoing municipal and county work occuring on the eastern third of the route, crews will return in Spring 2025 to finish the final coat of chip-seal paving from Palmryra Dr.(4000 S) to Main Street in West Springville.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-838-8363

Email: sr77paving@utah.gov

Stay Informed

To receive weekly construction updated, please contact the public informaiton team at the email address above and enter "Weekly Updates" in the subject line.