Overview

Project Overview

The Utah Department of Transportation (UDOT) will install a traffic signal at the intersection of Eagle Mountain Boulevard and State Route 73 (Cory B Wride Highway) beginning as early as Monday, April 20. This new configuration will be a High-T intersection, a 3-legged intersection allowing one direction of main-road traffic, in this case westbound, to flow through without stopping, while the opposite directions and side streets are signalized. The new intersection will also provide a free right from Eagle Mountain Boulevard to eastbound SR-73.

UDOT performed a traffic signal warrant study of the intersection that concluded that it meets the criteria necessary for a signal light to be installed. The installation of the signals will help improve turn movements for greater safety at the intersection.

Project Map

Image showing the location of the signal installation

High-T Intersection 

An image showing the new configuration of the intersection to a High-T

The new configuration of the SR-73 and Eagle Mountain Boulevard

 

For more information on how a High-T intersection works please click on the video below.

Schedule

Work Hours: 7 a.m. - 5 p.m.*

Workdays: Monday - Friday*

No weekend work unless noted*

In observance of the Memorial Day Holiday, no work will take place from Friday, May 22, through Tuesday morning, May 26. Enjoy the holiday!

Project Activities:

  • Asphalt paving along the south side will finish up next Thursday, May 28.
  • Monday night, June 8, beginning at 8 p.m. through 6 a.m. paving crews will work through the intersection. Traffic on SR-73 will be shifted to the north during this work. Eagle Mountain Boulevard will be closed during this night work for a separate Eagle Mountain City paving project. Motorists will be detoured to Old Airport Road for this work.
  • Signal pole installation is ongoing at the intersection through early June

*Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Construction: April 2026

Construction is anticipated to begin on Monday, April 20, 2026.

complete
complete

Design: 2024

Design is complete.

planned
planned

Completion: Late June 2026

This date is preliminary and is subject to change.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 855-925-2801 project code: 11888

Email: SR73eaglemountainsignal@utah.gov

 

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.