(Updated 8/2/22)

2022 CONSTRUCTION SCHEDULE

Estimated Start Date:   Tuesday, July 5; 

Construction Days:  Monday - Thursday; Except holidays

Construction Times:  Sunrise - Sunset

Estimated Completion Date:  Late August

Note: Schedules are subject to change due to weather and materials available

 

Construction Outlook

  • Chip seal and Fog coat overlay is complete!

 

(8/8 - 8/11)

  • Re-shouldering and grading roadway turnouts
  • Second coat of pavement paint messaging and lane striping application
  • Variable roadway traffic directional signs replaced and new safety signs installed

 

KEY PROJECT BENEFITS

  • Restoration of roadway surface by adding a chip-seal overlay
  • Leveled travel lanes
  • Realigned shoulders
  • New roadway and safety messaging signs
  • Widening of uphill shoulders for bicyclists safety
  • Various updated drainage controls

 

Image: @ MP 8 Looking South; First Coat Travel Lane Paint Lines Complete!

 

7/21/22  Chip application with fog seal coat finished product!

 

7/21/22  Chip Seal Fog Coating

 

7/13/21  Project description/notification at entrance to project - Little Dell Reservoir Trailhead

 

07/07/22  Hot Mix Asphalt Application - Northbound

07/07/22

07/07/22

UDOT PROJECT INFORMATION PAGE


LATEST TRAFFIC CONDITIONS

udottraffic.utah.gov 

or download the latest UDOT Traffic App.


FOR IMMEDIATE PROJECT INQUIRIES

Jeffrey Putzke, Public Involvement Manager

Phone:  801-652-4008

Email:  sr65renewed@utah.gov


OTHER NEARBY UDOT PROJECTS

I-80; 1300 E to 2300 E & I-215; 3300 S to 4500 S

[ CLICK HERE ]