Shoulder Work on SR-30 from Union Pacific Railraod (UPRR) to 1900 West
SR-30 construction began on Monday, July 8, on the south side of the road from the UPRR railroad tracks to 1900 West. During this phase, crews will be clearing tress and grubbing, working eastward.
Drivers in the area should anticipte rolling shoulder closures over the next few months for this operation. Flagging will be necessary at times to manage eastbound traffic entering town, allowing trucks to get back on the road safely.
No major activities are expected east of 1900 West until early fall. Work from 1000 West to 1900 West is anticipated to start in early fall, including relocating utility lines and installing water and sewer lines. All utility work is scheduled for completion this year, with final roadway reconstruction set for 2025.
We appreciate your patience and cooperation during this critical project. For real-time traffic updates, please visit the UDOT Traffic Website (https://udottraffic.utah.gov/) or download the UDOT Traffic App.
Project Overview
UDOT has designed improvements that will address traffic congestion and improve safety on SR-30, from SR-23 to 10th West (SR-252), based on the recently completed Corridor Study (see Corridor History Tab). Phase 2 work began in July 2024 with substantial completion expected in late 2025.
Traffic
With the growing population in Cache Valley, there is an increase in travel on SR-30, including freight travel. SR-30 is the only east-west roadway in Cache Valley so it is an important connection to the other major transportation routes in the area, especially I-15, US-89, and US-91 (Sardine Canyon). It is also an important truck route and is an alternative route to Cache Valley when US-89/US-91 is closed because of snow or an accident.
Corridor Concerns
The current area concerns include traffic/farm equipment crossing SR-30, traffic crossing lanes and potential for collisions, and lack of shoulders or sidewalks for walking and biking. The current design improves these concerns and provides a trail for recreational use.
Phase 2: Construction Phase (Summer 2024):
Additional travel lanes
Increased shoulder width
Flattened roadway side slopes
Bridge structure widening and construction of new drainage box culverts
New recreational trail on the south side of SR-30 and a sidewalk on the north side
Improvements at SR-23 intersection including an Advanced Warning System and intersection lighting
Contact Information