Project Description

The Utah Department of Transportation (UDOT) will resurface State Route 201 (2100 S) from 900 W to State Street. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface, address road imperfections and enhance motorist safety by providing a smoother, more durable road. Additional work includes upgraded pedestrian ramps to meet ADA compliance and refreshed lane painting/striping. 

 

New Pavement and lane striping | 400 W 2100 S | 07/28/25

Paving Operations | 2100 S and Main Street | 07/10/25

SR-201 Paving Map

Question title

Stay Informed

To receive occasional construction email updates, please enter your information below:

Schedule

live
live
Railway-Highway Construction Start: July 28, 2025

Work Hours: 7pm - 6am

Workdays: Sunday Night - Friday Morning

Note:  Varied daytime work from Aug. 11 - 22

Schedules are subject to change due to weather conditions and material availability.

See '2100 South Railway-Highway' tab for more information

planned
planned
Construction End: August 2025

Projects will be substantially complete end of August

complete
complete
Paving Construction Start: June 4, 2025

Work Hours: 7pm - 6am

Occasional daytime work as necessary: 6am - 10am

Workdays: Monday - Saturday

Schedules are subject to change due to weather conditions and material availability.

 

June: Upgrade pedestrian ramps for ADA compliance; Lower utility covers along travel lanes.

June 29: I-15 and SR-201 On-ramps will be closed as paving begins.

See impacts & updates tab for more information.

 