Overview

Project Overview

To roto-mill, resurface and improve the ride of the roadway, the Utah Department of Transportation (UDOT) will resurface SR-201 from I-80 to 9500 West. This work also includes drainage utility work to reduce standing water during rainstorm events.

 

Project Map

 

map image of SR-201 from I-80 to approximately 9500 West and surrounding landmarks of the Great Salt Lake, Kennecott and Saltair

Project Timeline

April 2026 through December 2026 engineering design work will take place for the SR-201 roadway surface and storm drain utility improvements.

 

Expect 

  • Occasional work from survey crews

  • Occasional drone flights for site reconnaissance. 

 

Stay Informed 

Subscribe to receive email updates by sending an email to sr201pavementimproved@utah.gov

 with “Updates” in the subject line.

 

Visit the project website: sr201pavementimproved@publicinput.com

 

Contact the public information team with questions or concerns at 888-704-4301 or sr201pavementimproved@utah.gov

Schedule

Daytime Work Hours: 7 a.m. - 5 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Design

April 2026 through December 2026 engineering design work will take place for the SR-201 roadway surface and storm drain utility improvements.

planned
planned

The design engineer and project team will be working from April 2026 through December 2026 to take into account all necessary existing conditions on this section of SR-201 from I-80 to 9500 West to prepare and design the road resurfacing and adjacent storm drain utility improvements.

complete
complete

Project Milestones

Contact Information

To contact the public information team with questions or concerns:

Hotline: 888-704-4301

Email: sr201pavementimproved@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at sr201pavementimproved@utah.gov and enter "Weekly Updates" in the subject line.