Overview

Project Introduction

UDOT and Navajo Nation Logos 

 

The Utah Department of Transportation (UDOT), in partnership with the Navajo Nation, has received a Nationally Significant Federal Lands and Tribal Projects Grant. The grant will be used to improve safety on SR-162 and SR-262 in San Juan County, Utah. Additional federal and state funding has been approved, with work tentatively scheduled to continue through 2026.

Project Purpose and Improvements

The project objectives are intended to improve safety and pavement along 53 miles of road in San Juan County between SR-162 and SR-262. Additional improvements include rebuilding multiple structures and other roadway-specific enhancements. This project will make travel safer, smoother, and more convenient for:

  • Residents in the area
  • Visitors traveling to Bears Ears, Four Corners, and Hovenweep National Monuments
  • Workers serving the petroleum extraction industry in the region

The following is a shortlist of key upgrades:

  • Improve pavement
  • Improve and/or install safety features such as guardrail, cattleguards, extra signage, protected turn lanes, and pavement markings
  • Widen lanes and/or add shoulders
  • Rebuild or improve several dozen culverts and flood mitigation infrastructure
  • Build a roundabout at the SR-162 and SR-262 intersection
  • Replace the SR-162 bridge over McElmo Creek
  • Install fiber-optic conduit
  • Install over 50 cattle guards at various roadway access points
  • Build a livestock crossing under SR-162

Stay Informed

To receive occasional construction email updates, please enter your information below:

Map showing construction area of SR-162/SR-262 from Bluff to Colorado boarder. UDOT PIN 17894

 

SR-262 Guardrail Installations | 01/14/26

 

McElmo Bridge Deck Forms.

McElmo Bridge Deck Forms | 06/24/25

 

Montezuma Creek Roundabout Grading

Montezuma Creek Roundabout Sub-Grading | 06/24/25

 

Three construction workers assembling headwall and culvert with the road of SR-262 above them.

Culvert Extension and Headwall Assembly | SR-262 | 02/10/25

 

Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.Shoulder Extension to prepare for road widening, showing dirt on side of the road on SR-262.
Shoulder Extensions | SR-262 | 02/10/25

 

 

New cattleguard with construction barrels around it and construction equipment behind.

Completed Cattleguard Installation | SR-162 @ Montezuma Creek | 02/10/25

 

Side of the road on SR-262 trenched out with an excavator in the background in order to install Fiber optic cable.

Trenching for Fiber Optic Conduit Installation | SR-262 | 02/10/25

Schedule

**5/22 - 5/25 Holiday Suspension for Memorial Day: All lanes open

  • Work Hours: 7:00 a.m. to 7:00 p.m.
  • Workdays: Monday through Friday (excluding holidays)

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Construction: August 2024 - August 2026

SR-262

US-191 to Montezuma Creek: All paving, guardrail installation, and roadside signage work are complete.  Spotty shoulder work remains with minimal traffic control required.

SR-162

Bluff to Montezuma Creek: All paving activity on main travel lanes complete.  Occasional short distance flagging operations using pilot car required.  Minor delays anticipated of 5-10 min.

Montezuma Creek to Aneth: Wide load and ground clearance restrictions discontinued as of May 4. All paving activity on travel lanes complete.  Minor shoulder work and occasional short distance flagging operations required.  Minimal delays expected.

Aneth to Colorado Border: All travel lane activity complete.  Possible shoulder work possible.

SR-162/262 Montezuma Creek Roundabout

Complete. Downlighting over the roundabout is anticipated to be installed on a date TBA. (updated)

Please see the Traffic Impacts tab for more details.

complete
complete

Milestones

Project Milestones

  • Contractor advertising (March/April 2024)
  • Contractor awarded (May 2024)
  • Groundbreaking event (August 13, 2024)
  • 70% of paving completed in 2025; work resumes in 2026
  • McElmo Bridge completed (November 2025)
  • Cattleguards installed (January 2026)
  • Roundabout grand opening (February 2026)
  • All major travel lane completed on SR-162/262 (May 2026)

Contact Information

To contact the Public Information Team with questions or concerns: