Overview

UDOT completed a project to replace two existing culverts that cross beneath SR-147 (7300 South) just west of 4850 West in Benjamin. Construction consisted of removing and replacing the larger box culvert for the Benjamin Slough and a smaller pipe culvert near the intersection to improve drainage in the area. 

Project Timeline

complete
complete

Start Construction: August 21, 2023

Work hours: 7 a.m. to 7 p.m.

Work days: Monday - Friday, and occasionally on weekends as needed

Schedules are subject to change due to weather conditions and material availability.

complete
complete

SR-147 ROAD CLOSURE (15 DAYS)

September 5-19

SR-147 (7300 South) will be CLOSED between the Benjamin Slough and 4850 West to all traffic.

Schedules are subject to change due to weather conditions and material availability.

complete
complete

SR-147 ROAD CLOSURE (2 DAYS)

October 12-13

SR-147 (7300 South) will be CLOSED between the Benjamin Slough and 4850 West to all traffic. (See Impacts & Updates tab for more information.

Schedules are subject to change due to weather conditions and material availability.

complete
complete

End Construction - October 26, 2023

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-557-2585

Email: udotregion3@utah.gov

Stay Informed

To receive construction updates, please contact the public information team at the email address above and enter "SR-147 Culverts" in the subject line.