Overview

Project Overview

Crews are continuing to make good progress on the installation of six new cattleguards. Currently, there is a temporary traffic light installed for traffic management, which will be removed during the paving of the roads. The cattleguards will be fully completed by June 15.

 

Lane leveling will start at the south end of the project towards Cedar Breaks on June 15. Lane leveling is the process of filling in the wheel-path and other road surface imperfections. This will make the roads more even, and easier to pave and traverse once paving begins. During this process, the crews will cover approximately five miles a day.

 

Please slow down and follow all traffic control.

 

Crews are hard at work replacing the old cattle guards.

The newly installed cattle guards.

 

Project Map

The project area is depicted above. It will run for ten miles.

 

Schedule

Work Hours: 7 a.m. - 7 p.m.

Workdays: Monday - Friday

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: (435) 288-2689

Email: sr143improved@utah.gov

Project Timeline

live
live

Design

This project will make improvements to SR-143 near Cedar Breaks National Monument. Traffic will be impacted during construction hours and motorists should plan for 15 minute delays in each direction. 

planned
planned

Construction Start Date

Construction has begun as of Monday, May 18, 2026. Crews will be working Monday through Friday from 7 a.m. to 7 p.m. 

complete
complete

Project Milestones

Designed improvements have been finished and our contractor has begun construction on Monday, May 18, 2026. 

Stay Informed

Please check this site periodically for the latest information.