Skip Navigation
 

SR-13 | Corinne to I-15 | Renewed

SR-13 | Corinne to I-15 | Renewed

UDOT preserved the pavement on SR-13 between I-15 and SR-83.

Overview

Construction Complete

This project was completed on August 14, 2026.

Questions?

UDOT Region 1 office 801-620-1600
Mon - Fri, 8:00 a.m. - 5:00 p.m.


Project Overview

UDOT renewed approximately four miles of SR-13 and SR-83 through Corinne (see map below) by placing an asphalt surface treatment called a Bonded Wearing Course (BWC). A BWC is used to extend the life of the existing pavement, while also restoring skid resistance and sealing the road surface to improve drainage. This project also included removing and replacing pedestrian ramps to bring them up to current ADA standards, replacing barrier, and updating road signs, lighting, striping, and rumble strips.
 

Project Map

PIN 20886 | Road construction map of the project taking place on SR-13 through Corinne, from I-15 to the Walmart Distribution Center
 

Project Timeline

  • Construction began on June 15, 2026, and reached substantial completion in mid-August 2026.

Project Timeline

complete
complete

This project is complete.

complete
complete

Project Milestones

  • June 15, 2026: Construction began.
  • June 24, 2026: Concrete work was completed.
  • July 23, 2026: Asphalt paving operations were completed.
  • Mid-August 2026: Project reached substantial completion.