SR-132 Project Update

Construction is nearing completion on the SR-132 Safety Project.

What to Expect in the Coming Week

Crews are nearing completion of the SR-132 improvements and expect to finish in about 10 days, weather permitting.

Starting Tuesday, May 13 crews will begin removing old asphalt and applying a new micro surface layer. Once each day’s paving is complete, striping crews will follow to place final lane markings. Work is expecting to continue through Saturday, May 17.

Expect minor delays due to one-way flagging operations to accommodate construction activity.

For your safety and to help keep the project on schedule, please obey all posted signs and detours.

Upcoming Schedule Highlights:

  • May 13-17: Crews will apply the final layer of roadway surface, called microsurface. Final pavement striping will be completed following this work.

Thank you for your patience as we complete this work!

Project Recap

  • Improved roadway shoulders by flattening slopes

  • Added a lane between MP 37 and 38, extending two existing passing lanes into one continuous section

  • Constructed several retaining walls to accommodate the wider roadway and shoulders

  • Replaced significant portions of Nephi City’s water line

Construction is anticipated to continue through Spring 2025.

Schedule

The contractor is planning to complete the major portions of the project as earlly as May 17 when they apply the final asphalt surface and complete lane striping. This work will take place Tuesday May 13 through Saturday, May 17. Schedule is subject to change.

Stay Informed

To receive weekly construction updated, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 801-712-3030

Email: sr132@utah.gov

Website: https://udotinput.utah.gov/sr132