This project is complete. We would like to thank you for your patience and cooperation during construction, and invite you to send any feedback, questions, or concerns regarding this project to our team using the contact information found in the sidebar.


Project Background

UDOT constructed a project to renew SR-126 (Main/State Street) from I-15 at Layton Parkway to 300 North in Clearfield. The project entailed removing and replacing the top layer of asphalt in certain areas where the pavement was in bad condition, as well as placing a new asphalt surface along the entire corridor. The project also included installing new sidewalk pedestrian ramps to meet ADA standards. 

This project extended the life of the existing asphalt and provided a better driving experience for motorists along the corridor.

Work began on June 24, 2024 and concluded at the end of October 2024.

Schedule

complete
complete
Concrete Work: June 24, 2024 to August 2024

Work Hours: 7 a.m. - 5 p.m.

Work Days: Monday - Friday

Daily shoulder closures are expected along the corridor during this work. Pedestrian detour routes will also be in place.

Schedules are subject to change due to weather conditions and material availability

complete
complete
Paving: August to October 2024

Work will take place up to seven days a week, between the hours of 9 p.m. and 7 a.m.

During work hours, motorists can expect lane closures, lane shifts, and short delays.

Schedules are subject to change due to weather conditions and material availability.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 877-495-4240

Email: udotregion1@utah.gov