Traffic Alert

As early as Sept. 2 through late September, we will reduce State Route 126 to a single lane, alternating one-way on weekdays, from 7 a.m. to 7 p.m., as part of the SR-126 Paving project. This lane closure will take place on weekdays and is needed to accommodate road paving activities. The location of the closure will vary as paving activities progress. Partial ramp closures on I-15 are planned for mid-September.

Labor Day Holiday Schedule
In observance of the Labor Day holiday, no work will take place in the project area beginning the afternoon of Friday, Aug. 29, through Monday, Sept. 1.

 

Overview

The Utah Department of Transportation (UDOT) is repaving eight miles of State Route 126 between State Route 39 (1200 South) and U.S. Route 89 from Marriott-Slaterville to South Willard, Utah. The project is helping improve the pavement conditions, extend the life of the road, and enhance the driving experience for all users. Additional work includes restriping access ramps, bridge repairs, and replacing outdated signs along the corridor.

Three images with the paved road and crews working on paving activities.

Project Area

 

Project Updates


Aug. 29, 2025


As early as Sept. 2 through late September, we will reduce State Route 126 to a single lane, alternating one-way on weekdays, from 7 a.m. to 7 p.m., as part of the SR-126 Paving project. This lane closure will take place on weekdays and is needed to accommodate road paving activities. The location of the closure will vary as paving activities progress. Partial ramp closures on I-15 are planned for mid-September.

Drivers can expect: 

  • Roadwork Monday through Friday, from 7 a.m. to 7 p.m., and some nightwork on weekends
  • Flaggers and a pilot car to direct traffic
  • Minor delays 
  • Increased noise, dust, and vibration near the project area
  • Partial ramp closures on I-15

Plan Your Travel
To avoid delays in the project area, plan ahead, travel before or after construction work hours, and use alternate routes when possible. Drivers are advised to stay alert and remain cautious through these areas as heavy equipment enters and exits the work zone. Visit udottraffic.utah.gov or download the UDOT Traffic mobile app for up-to-date traffic information.


Aug. 18, 2025

Traffic alert. Weekday Lane closures. Aug. 21 - 29

Beginning as early as Aug. 21 through Aug. 29, we will reduce State Route 126 to a single lane alternating one-way on weekdays as part of the SR-126 Paving project. This lane closure will take place on weekdays, from 9 a.m. to 4 p.m., and is needed to accommodate road paving activities. The location of the closure will vary as paving activities progress.

Drivers can expect: 

  • Flaggers and a pilot car to direct traffic
  • Minor Delays 
  • Loose gravel and dust
  • Noise and vibration

Drivers are advised to stay alert and remain cautious through these areas as heavy equipment enters and exits the work zone. Please plan ahead to avoid potential delays due to the lane closures or seek alternate routes. 


Aug. 8, 2025Detour map with routes for eastbound and westboud drivers. Eastbound and westbound closure of Pioneer Road intersection.

On Sunday, Aug. 10, from 6 a.m. to 6 p.m., there was an eastbound and westbound closure at the intersection of State Route 126 (1900 W.) and Pioneer Road (400 N.) in Marriott-Slaterville. This closure was needed to accommodate road paving activities. Please use caution, expect some travel delays and follow posted detours routes.  

 

Aug. 3 – 6, 2025

Eastbound and westbound nightly closures occurred at the intersection of State Route 126 (1900 W.) and Pioneer Road in Marriott-Slaterville from 7 p.m. to 6 a.m. This closure was needed to accommodate paving and project activities. Please use caution, follow posted detours, and expect some travel delays.  


July 31, 2025

Roadwork will take place at night for the first week and during the day throughout the project. Motorists can expect lane closures, detours, and slower traffic through work zones.  There will be at least one full closure of 400 North during the first week of the project. Please use caution, follow posted detours, and allow a little extra time if traveling in the area when construction is happening. 

Project Information

Hotline: 385-279-2779

Email: sr126paving@utah.gov

 

Schedule

August - Late September

Workdays: Monday - Friday

Work Hours: 7 a.m. - 7 p.m.

Some night work on weekends. 

Schedules are subject to change due to weather conditions and material availability.

live
live
Construction

Construction began on Aug. 3, 2025. Crews are resurfacing the pavement on State Route 126. The project will remove surface defects and increase road longtevity. 

planned
planned
Construction – August 2025 – September 2025

 

  • Road Surface Removal
  • Road Surface Repaving
  • Sign Installs
  • Pavement Surface Treatment
  • Striping
  • Late September – Project Completion

 

complete
complete
Project Milestones

  • 8/3/2025: Construction Begins
  • 8/3/2025 – 8/6/2025: Nightly Eastbound/Westbound Pioneer Road Intersection Closures
  • 8/10/2025 – Daytime Eastbound/Westbound Pioneer Road Intersection Closure 

Contact Information

To contact the public information team with questions or concerns:

Hotline: 385-279-2779

Email: sr126paving@utah.gov