Construction Update (Thursday, March 20, 2025)

The speed limit along SR-30 in active work areas has been reduced to 50 mph. Drivers should follow the posted speed limit. 

Sidewalk/roadway Closure For Storm Drain Work

Starting as early as Monday, March 24, crews will begin storm drain work and close the sidewalk along the north side of SR-30 between 10th West and approximately 1200 West. Pedestrians can use sidewalks along the east side of Maverik and 250 North to get around the closure.

As part of this work, crews will close the southern access to 250 North (between Maverik and Extra Space Storage) from Monday, March 24, through Friday, March 28. After that road reopens, crews will close Maverik's southern entrance from SR-30 from Monday, March 31, through Friday, April 4.

Expect active work along the sidewalk and park strips on the north side of SR-30 from 10th West to approximately 1200 West between March 24 and April 11.


Nighttime Sewer Work

Crews will begin sewer work at night, which will require closures along SR-30. A flagging operation will be in place on Wednesday and Thursday night.

Beginning Sunday, March 30, crews will start intermittent nightly SR-30 closures from 8 p.m. through 5 a.m., Sunday night through Friday morning. These periodic closures will take place through summer 2025.

During these closures, eastbound SR-30 drivers will detour to 600 South via 1900 West, then back to SR-30 via 10th West. Westbound drivers will take 10th West to 200 South, then 1900 West back to SR-30. Please follow posted signage and watch for flaggers. Local traffic only will be allowed between 10th West and Gateway Drive during the closures.

Trucks and heavy vehicles should follow the signed detour route to reduce turning movement conflicts.


Road Surface Repairs

Work is ongoing to fix the rough roadway near the Logan City Landfill. Drivers should slow down and watch for flaggers and work crews in the area while they work to patch the impacted area.

Lanes at SR-30 and SR-23 have been shifted to the north in order to accommodate construction of the pedestrian underpass.  Crews restriped lane lines and patched the temporary pavement on Friday, Feb. 28. Crews are also working to patch the roadway near SR-23.


Ongoing Project Work

Crews are currently installing conduits and junction boxes for traffic information systems between 1900 West and 10th West. Work is underway for new traffic signals on all four corners at 10th West and crews will be potholing on 10th West at night this week.

Storm drain and irrigation work is underway between 1500 West and 1400 West before shifting to the work near Maverik beginning March 24.

Work on the Logan River Dock parking lot has started and the entrance and parking lot will be temporarily reconfigured. This work and temporary reconfiguration will remain in place until spring 2025. 

Work is underway on the pedestrian underpass at the intersection of SR-30 and SR-23. Crews have poured the concrete floor of the pedestrian structure and will install a temporary retaining wall this week.

Logan Power is relocating power lines to underground conduits and is currently working between the auto salvage yard and 10th West. 

complete
complete
Design (2018)

complete
complete
Phase 1: Construction Preparation (2023)

live
live
Phase 2: Construction (2024 - 2025)

Contact Information

To contact the public information team with questions or concerns:

  • Hotline: 435-774-0700
  • Email: sr30@utah.gov
  • Website: udotinput.utah.gov/SR30