Impacts & Updates

Update: March 11, 2026

Project On Track to Begin Construction in Spring 2027

Design of the new I-15 South Cedar Interchange continues to progress as planned and has reached 60% completion.

Through spring 2026, UDOT will continue acquiring the right-of-way needed for this project. Coordination with utility owners is ongoing to identify and redesign any affected systems. Environmental survey work is also underway, and you may see crews performing surveys in areas surrounding the interchange. 

This summer, project design will continue advancing toward 90% completion. 

Noise Evaluation

Noise evaluations conducted as part of the project's environmental review identified areas that qualify for further evaluation. The team will be reaching out to affected properties about next steps.

Schedule

Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

Complete Design (Summer 2026)

Design is anticipated to finish by late summer 2026, and a contractor is anticipated to be selected in fall 2026. 

planned
planned

Construction (Anticipated Spring 2027- Winter 2028)

complete
complete

Project Milestones

Contact Information

To contact the public information team with questions or concerns:

Hotline: 435-599-7739

Email: southcedar@utah.gov

Stay Informed

To receive updates, please contact the public information team at the email address above and enter "Updates" in the subject line.